| A | B | C | D | E | F | G | I | |
|---|---|---|---|---|---|---|---|---|
| 1 | PRELIMINARY COST ESTIMATE | |||||||
| 2 | ||||||||
| 3 | Sheridan Street Improvement Project - Newberg | |||||||
| 4 | ||||||||
| 5 | ITEM # | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | AMOUNT | ||
| 6 | ||||||||
| 7 | ||||||||
| 8 | GENERAL | |||||||
| 9 | 1 | Mobilization (include performance & payment bonds, maintenance warranty bond, insurance, city business permit and all other permits) | LS | 1 | $ 7,000.00 | $ 7,000.00 | ||
| 10 | 2 | Traffic Control (include RR flagging as needed, barricades, temporary signage) | LS | 1 | $ 5,000.00 | $ 5,000.00 | ||
| 11 | 3 |
Erosion & Sediment Control Measures |
LS | 1 | $ 1,000.00 | $ 1,000.00 | ||
| 12 | 4 | Construction Staking (for curb, etc.) | LS | 1 | $ 2,000.00 | $ 2,000.00 | ||
| 13 | 5 | Site Restoration & Cleanup | LS | 1 | $ 1,000.00 | $ 1,000.00 | ||
| 14 | Subtotal for GENERAL = | $ 16,000 | ||||||
| 15 | DEMOLITION | |||||||
| 16 | 6 | Remove Concrete Sidewalk (include sawcut, haul off and disposal) | SF | 6476 | $ 1.25 | $ 8,095.00 | ||
| 17 | 7 | Remove Asphalt Concrete to Full Depth (include sawcut, haul off and disposal) | SF | 14002 | $ 1.00 | $ 14,002.00 | ||
| 18 | 8 |
Remove Concrete Curb/Gutter (include sawcut, haul off and disposal) |
LF | 993 | $ 2.50 | $ 2,482.50 | ||
| 19 | 9 | Stripping & Excavation (include earthwork, haul off and disposal) | SY | 3256 | $ 3.00 | $ 9,770.00 | ||
| 20 | 10 | Remove, Relocate &/or Reinstall Signs & Mailboxes | LS | 1 | $ 1,000.00 | $ 1,000.00 | ||
| 21 | Subtotal for DEMOLITION = | $ 35,350 | $ 36,614.78 | |||||
| 22 | ROAD IMPROVEMENTS | |||||||
| 23 | 11 | Standard Concrete Curb | LF | 96 | $ 12.00 | $ 1,152.00 | ||
| 24 | 12 | Rolled Concrete Curb | LF | 884 | $ 10.00 | $ 8,840.00 | ||
| 25 | 13 | Concrete Sidewalk (4" thick over 2" of 3/4"-0 crushed rock over compacted subgrade) | SF | 14504 | $ 3.50 | $ 50,764.00 | ||
| 26 | 14 |
Concrete Paver (4" thick over 2" of 3/4"-0 crushed rock over compacted subgrade) |
SF | 14276 | $ 6.00 | $ 85,656.00 | ||
| 27 | 15 |
Concrete Handicap Ramp (Including 2' wide tactile warning surface) |
EA | 8 | $ 1,350.00 | $ 10,800.00 | ||
| 28 | 16 | Bedding Layer, 2" Depth | SY | 1586 | $ - | $ - | ||
| 29 | 17 | Choker Rock, 4" Depth (AASHTO #57) | SY | 1586 | $ - | $ - | ||
| 30 | 18 | Base Rock, 12" Depth (#2) | SY | 1586 | $ - | $ - | ||
| 31 | 19 | Compaction Tests (for roadway) | EA | 12 | $ 65.00 | $ 780.00 | ||
| 32 | Subtotal for ROAD IMPROVEMENTS = | $ 157,992 | ||||||
| 33 | TRAFFIC SIGNING AND STRIPING | |||||||
| 34 | 20 | Street Signs | LS | 1 | $ 1,500.00 | $ 1,500.00 | ||
| 35 | 21 | Pavement Markers/Reflectors | LS | 1 | $ 3,500.00 | $ 3,500.00 | ||
| 36 | Subtotal for TRAFFIC SIGNING AND STRIPING = | $ 5,000 | ||||||
| 37 | LANDSCAPE & IRRIGATION | |||||||
| 38 | 22 | Street Trees (include tree wells & steel grates) | EA | 16 | $ 950.00 | $ 15,200.00 | ||
| 39 | 23 |
Place Top Soil, Barkdust, & Soil Mix |
LS | 1 | $ 1,500.00 | $ 1,500.00 | ||
| 40 | 24 |
Landscape & Irrigation |
LS | 1 | $ 4,000.00 | $ 4,000.00 | ||
| 41 | 25 | Decorative Bollards for Street Closure/Cultural Center Event | LS | 1 | $ 4,000.00 | $ 4,000.00 | ||
| 42 | Subtotal for LANDSCAPE & IRRIGATION = | $ 24,700 | ||||||
| 43 | UTILITIES | |||||||
| 44 | Storm System Improvements | |||||||
| 45 | 26 | Drainage or Underdrain Enhancement | LS | 1 | $ 8,000.00 | $ 8,000.00 | ||
| 46 | Subtotal for STORM SYSTEM IMPROVEMENTS = | $ 8,000 | ||||||
| 47 | Power & Lighting Improvements | |||||||
| 48 | 27 | Ornamental Sidewalk or Street Lighting (at every 75') | EA | 12 | $ 3,800.00 | $ 45,600.00 | ||
| 49 | 28 | Relocate & Underground Overhead Utilities (reconnect as needed) | LS | 1 | $ 20,000.00 | $ 20,000.00 | ||
| 50 | Subtotal for POWER & LIGHTING IMPROVEMENTS = | $ 65,600 | ||||||
| 51 |
|
|||||||
|---|---|---|---|---|---|---|---|---|
| 52 | 29 | Engineering Survey & Design | LS | 1 | $ 18,000.00 | $ 18,000.00 | ||
| 53 | 30 | Construction Management | LS | 1 | $ 8,000.00 | $ 8,000.00 | ||
| 54 | 31 | Contingency (approx. 10%) | LS | 1 | $ 30,000.00 | $ 30,000.00 | ||
| 55 | Subtotal for OTHER COSTS = | $ 56,000 | ||||||
| 56 | TOTAL = | $ 368,641.50 | ||||||
| A | B | C | D | E | F | G | |
|---|---|---|---|---|---|---|---|
| 1 | PRELIMINARY COST ESTIMATE | ||||||
| 2 | |||||||
| 3 | Sheridan Street Improvement Project - Newberg | ||||||
| 4 | |||||||
| 5 | ITEM # | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | AMOUNT | |
| 6 | |||||||
| 7 | |||||||
| 8 | GENERAL | ||||||
| 9 | 1 | Mobilization (include performance & payment bonds, maintenance warranty bond, insurance, city business permit and all other permits) | LS | 1 | $ 7,000.00 | $ 7,000.00 | |
| 10 | 2 | Traffic Control (include RR flagging as needed, barricades, temporary signage) | LS | 1 | $ 5,000.00 | $ 5,000.00 | |
| 11 | 3 |
Erosion & Sediment Control Measures |
LS | 1 | $ 1,000.00 | $ 1,000.00 | |
| 12 | 4 | Construction Staking (for curb, etc.) | LS | 1 | $ 2,000.00 | $ 2,000.00 | |
| 13 | 5 | Site Restoration & Cleanup | LS | 1 | $ 1,000.00 | $ 1,000.00 | |
| 14 | Subtotal for GENERAL = | $ 16,000 | |||||
| 15 | DEMOLITION | ||||||
| 16 | 6 | Remove Concrete Sidewalk (include sawcut, haul off and disposal) | SF | 6476 | $ 1.25 | $ 8,095.00 | |
| 17 | 7 | Remove Asphalt Concrete to Full Depth (include sawcut, haul off and disposal) | SF | 14002 | $ 1.00 | $ 14,002.00 | |
| 18 | 8 |
Remove Concrete Curb/Gutter (include sawcut, haul off and disposal) |
LF | 993 | $ 2.50 | $ 2,482.50 | |
| 19 | 9 | Stripping & Excavation (include earthwork, haul off and disposal) | SY | 3256 | $ 3.00 | $ 9,770.00 | |
| 20 | 10 | Remove, Relocate &/or Reinstall Signs & Mailboxes | LS | 1 | $ 1,000.00 | $ 1,000.00 | |
| 21 | Subtotal for DEMOLITION = | $ 35,350 | |||||
| 22 | ROAD IMPROVEMENTS | ||||||
| 23 | 11 | Standard Concrete Curb | LF | 96 | $ 12.00 | $ 1,152.00 | |
| 24 | 12 | Rolled Concrete Curb | LF | 884 | $ 10.00 | $ 8,840.00 | |
| 25 | 13 | Concrete Sidewalk (4" thick over 2" of 3/4"-0 crushed rock over compacted subgrade) | SF | 14504 | $ 3.50 | $ 50,764.00 | |
| 26 | 14 |
Concrete Paver (4" thick over 2" of 3/4"-0 crushed rock over compacted subgrade) |
SF | 14276 | $ 3.50 | $ 49,966.00 | |
| 27 | 15 |
Concrete Handicap Ramp (Including 2' wide tactile warning surface) |
EA | 8 | $ 1,350.00 | $ 10,800.00 | |
| 28 | 16 | Leveling Rock, 3" Depth (3/4"-0) | SY | 1586 | $ 2.50 | $ 3,965.00 | |
| 29 | 17 | Base Rock, 12" Depth (1-1/2"-0) | SY | 1586 | $ 7.50 | $ 11,895.00 | |
| 30 | 18 | Compaction Tests (for roadway) | EA | 12 | $ 65.00 | $ 780.00 | |
| 31 | Subtotal for ROAD IMPROVEMENTS = | $ 138,162 | |||||
| 32 | TRAFFIC SIGNING AND STRIPING | ||||||
| 33 | 19 | Street Signs | LS | 1 | $ 1,500.00 | $ 1,500.00 | |
| 34 | 20 | Pavement Markers/Reflectors | LS | 1 | $ 3,500.00 | $ 3,500.00 | |
| 35 | Subtotal for TRAFFIC SIGNING AND STRIPING = | $ 5,000 | |||||
| 36 | LANDSCAPE & IRRIGATION | ||||||
| 37 | 21 | Street Trees (include tree wells & steel grates) | EA | 16 | $ 650.00 | $ 10,400.00 | |
| 38 | 22 |
Place Top Soil, Barkdust, & Soil Mix |
LS | 1 | $ 1,500.00 | $ 1,500.00 | |
| 39 | 23 |
Landscape & Irrigation |
LS | 1 | $ 4,000.00 | $ 4,000.00 | |
| 40 | 24 | Decorative Bollards for Street Closure/Cultural Center Event | LS | 1 | $ 4,000.00 | $ 4,000.00 | |
| 41 | Subtotal for LANDSCAPE & IRRIGATION = | $ 19,900 | |||||
| 42 | UTILITIES | ||||||
| 43 | Storm System Improvements | ||||||
| 44 | 25 | Drainage or Underdrain Enhancement | LS | 1 | $ 8,000.00 | $ 8,000.00 | |
| 45 | Subtotal for STORM SYSTEM IMPROVEMENTS = | $ 8,000 | |||||
| 46 | Power & Lighting Improvements | ||||||
| 47 | 26 | Ornamental Sidewalk or Street Lighting (at every 75') | EA | 12 | $ 3,800.00 | $ 45,600.00 | |
| 48 | 27 | Relocate & Underground Overhead Utilities (reconnect as needed) | LS | 1 | $ 20,000.00 | $ 20,000.00 | |
| 49 | Subtotal for POWER & LIGHTING IMPROVEMENTS = | $ 65,600 | |||||
| 50 |
|
||||||
| 51 | 28 | Engineering Survey & Design | LS | 1 | $ 18,000.00 | $ 18,000.00 | |
|---|---|---|---|---|---|---|---|
| 52 | 29 | Construction Management | LS | 1 | $ 8,000.00 | $ 8,000.00 | |
| 53 | 30 | Contingency (approx. 10%) | LS | 1 | $ 30,000.00 | $ 30,000.00 | |
| 54 | Subtotal for OTHER COSTS = | $ 56,000 | |||||
| 55 | TOTAL = | $ 344,011.50 | |||||
| A | B | C | D | E | F | G | |
|---|---|---|---|---|---|---|---|
| 1 | PRELIMINARY COST ESTIMATE | ||||||
| 2 | |||||||
| 3 | Cultural Center Improvement Project - Newberg | ||||||
| 4 | |||||||
| 5 | ITEM # | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | AMOUNT | |
| 6 | |||||||
| 7 | |||||||
| 8 | GENERAL | ||||||
| 9 | 1 | Mobilization (Including performance & payment bonds, maintenance warranty bond, insurance, city business permit and all other permits) |
LS | 1 | $ 7,000.00 | $ 7,000.00 | |
| 10 | 2 |
Traffic Control (Including RR Flagging) |
LS | 1 | $ 6,000.00 | $ 6,000.00 | |
| 11 | 3 |
Erosion & Sediment Control Measures |
LS | 1 | $ 1,000.00 | $ 1,000.00 | |
| 12 | 4 | Stripping & Excavation (Including sawcut, removal, haul off, and disposal of existing asphalt, and concrete material; and minor earthwork) |
SY | 6690 | $ 3.50 | $ 23,420.00 | |
| 13 | 5 | Remove &/or Relocate Signs & Mailboxes | LS | 1 | $ 500.00 | $ 500.00 | |
| 14 | 6 | Site Restoration & Cleanup | LS | 1 | $ 800.00 | $ 800.00 | |
| 15 | 7 | Survey Staking (For curb, etc.) |
LS | 1 | $ 2,500.00 | $ 2,500.00 | |
| 16 | Subtotal for GENERAL = | $ 41,220 | |||||
| 17 | ROAD IMPROVEMENTS | ||||||
| 18 | 8 | Type A Curb & Gutter | LF | 1043 | $ 7.00 | $ 7,301.00 | |
| 19 | 9 | Concrete Sidewalk (4" thick over 2" of 3/4"-0 crushed rock over compacted subgrade) |
SF | 4101 | $ 3.50 | $ 14,353.50 | |
| 20 | 10 | Concrete Handicap Ramp (Including 2' wide tactile warning surface) |
EA | 8 | $ 1,300.00 | $ 10,400.00 | |
| 21 | 11 | Grind 2" Asphalt: Blaine Street | SY | 1859 | $ 4.00 | $ 7,436.00 | |
| 22 | 12 | Grind 2" Asphalt: Sherman Street | SY | 1624 | $ 4.00 | $ 6,496.00 | |
| 23 | 13 | Grind All Asphalt: Sheridan Street | SY | 1561 | $ 4.00 | $ 6,244.00 | |
| 24 | 14 | Hot Mix Asphalt, Class C (3" overlay in 2 lifts): Blaine Street | SY | 1859 | $ 15.00 | $ 27,885.00 | |
| 25 | 15 | Hot Mix Asphalt, Class C (3" overlay in 2 lifts): Sherman Street | SY | 1624 | $ 15.00 | $ 24,360.00 | |
| 26 | 16 | Stamped Concrete or Paver: Sheridan Street | SY | 1561 | $ 30.00 | $ 46,830.00 | |
| 27 | 17 | Hot Mix Asphalt, Class C (3" in 2 lifts): Blaine Street | SY | 421 | $ 15.00 | $ 6,315.00 | |
| 28 | 18 | Hot Mix Asphalt, Class C (3" in 2 lifts): Sherman Street | SY | 705 | $ 15.00 | $ 10,575.00 | |
| 29 | 19 | Base Rock, 9" Depth (1-1/2"-0): Blaine Street | SY | 421 | $ 6.00 | $ 2,526.00 | |
| 30 | 20 | Base Rock, 9" Depth (1-1/2"-0): Sherman Street | SY | 705 | $ 6.00 | $ 4,230.00 | |
| 31 | 21 | Leveling Rock, 3" Depth (3/4"-0): Blaine Street | SY | 421 | $ 2.50 | $ 1,052.50 | |
| 32 | 22 | Leveling Rock, 3" Depth (3/4"-0): Sherman Street | SY | 705 | $ 2.50 | $ 1,762.50 | |
| 33 | 23 | Compaction Tests (for roadway) |
EA | 12 | $ 50.00 | $ 600.00 | |
| 34 | Subtotal for ROAD IMPROVEMENTS = | $ 178,367 | |||||
| 35 | TRAFFIC SIGNING AND STRIPING | ||||||
| 36 | 24 | Street Signs | LS | 1 | $ 500.00 | $ 500.00 | |
| 37 | 25 | Pavement Striping | LS | 1 | $ 8,000.00 | $ 8,000.00 | |
| 38 | Subtotal for TRAFFIC SIGNING AND STRIPING = | $ 8,500 | |||||
| 39 | LANDSCAPING & WALLS | ||||||
| 40 | 26 | Place Top Soil, Barkdust, & Soil Mix | LS | 1 | $ 5,500.00 | $ 5,500.00 | |
| 41 | 27 |
Landscape & Irrigation |
LS | 1 | $ 5,000.00 | $ 5,000.00 | |
| 42 | 28 | 2'x2' Retaining Wall | SF | 471 | $ 25.00 | $ 11,775.00 | |
| 43 | Subtotal for LANDSCAPING AND WALLS = | $ 22,275 | |||||
| 44 | UTILITIES | ||||||
| 45 | Storm System Improvements | ||||||
| 46 | 29 | Install Concrete Valley Gutter | LF | 717 | $ 14.00 | $ 10,038.00 | |
| 47 | Subtotal for STORM SYSTEM IMPROVEMENTS = | $ 10,038 | |||||
| 48 | Power & Lighting Improvements | ||||||
| 49 | 30 | Street Lighting (At every 150'; Westbrooke style, HPS, flat lens Luminaire mounted on 18' black aluminum smooth pole) |
EA | 6 | $ 4,500.00 | $ 27,000.00 | |
| 50 | 31 | Power Relocation (Underground power & house feed reconnection) |
LS | 1 | $ 10,000.00 | $ 10,000.00 | |
| 51 | Subtotal for POWER & LIGHTING IMPROVEMENTS = | $ 37,000 | |||||
|---|---|---|---|---|---|---|---|
| 52 |
|
||||||
| 53 | 32 | Engineering Survey & Design | LS | 1 | $ 15,000.00 | $ 15,000.00 | |
| 54 | 33 | Construction Management | LS | 1 | $ 8,000.00 | $ 8,000.00 | |
| 55 | 34 | Contingency (12%) | LS | 1 | $ 45,000.00 | $ 45,000.00 | |
| 56 | Subtotal for OTHER COSTS = | $ 68,000 | |||||
| 57 | TOTAL = | $ 365,399.50 | |||||