1 CHANGE ORDER (CONTRACT MODIFICATION WITH DETAIL)
2
      Change Order No. 002
3   Engineering Services Department      
4 P.O. Box 970 · 414 E. First Street · Newberg, Oregon 97132 · 503.537.1240 · Fax 503.537.1277  
5              
6 Project: Aquarius Wastewater Lateral Replacement Projecr Date: June 6, 2016
7 Funding A/C: #04.5150.7063012 & 06.5132.538301 Contractor: The Saunders Company
8 P.O. No. 8172 (for original contract)          
9              
10 CHANGE ORDER DETAIL          
11 Details for this change order outline total compensation for all items in Change Order No. 1, including material, labor, equipment and profit. No additional work days are added to the contract for this change order. The following modifications to the contract are hereby ordered:
12              
13 Item #2-01. Contract was for the replacement of the wastewater laterals. This work is completed with only restoration work left to perform. This change order will add to the scope of work by adding repair work on the existing wastewater line at the intersection of Coffee Ln and Aquarius. During routine video inspection Publis Works Maintenece found a section of mainline with two holes in the top of the pipe and two cracked lateral connections. This change order will remedy the infiltration of ground water in this section of mainline by replacing approximatly 39 feet of 8" concrete pipe with 3034 PVC pipe and two 8" X 6" tees. See the cost of these changes below:
14
15 C.O. Item # Description for
Change Order Item
Unit Estm Qnty Unit Price Subtotal  
16 2-01 Cost to repair/replace approx. 39 feet of mainline and two lateral tees. LS 1 13,695.73 $ 13,695.73  
17  
Total =
      $ 13,695.73  
18              
19              
20 THIS CHANGE ORDER          
21              
22              
23              
24              
25              
26              
27              
28 Original Construction Bid Total ** =     $148,030.50  
29 Total billable per quatites of original contract =   $1,107.77  
30 This Change (see itemized detail above) ** =   $13,695.73  
31 Revised Contract Total ** =   $162,834.00 10.00%
32 Original Full Completion Date =   6/30/2016    
33 ** Subject to increase or decrease in quantities per construction.      
34              
35              
36              
37              
38 Prepared by: Accepted by:      
39   Project Manager Date:   Contractor    
40              
41 Approved by:          
42   City Engineer Date:   Title   Date:
43              
44 Approved by:          
45   Public Works Director Date:        
46              
47 Approved by:          
48   City Manager Pro Tem Date:        
49              
50              
51              
52              
53              
54              
55              
56              
57              
58              
59              
60              
61              
62              
63              
64              
65              
66              
67              
68              
69 THIS CHANGE ORDER          
70 Change Order Items Summary Descriptions Addition Deduction  
71 CO 1-01 Credit for epoxy coating of 10" pump column (relates to Bid Item #20). - $975.00  
72 CO 1-02 Provide 120 LF cable extension and splice kit for the existing pump. $2,350.00 -  
73 CO 1-03 (a) Lump sum credit for aquifer testing.   $6,263.00  
74   (b) Credit for test pumping at $39.00/hr for estimated 56 hours.   $2,184.00  
75   (c) Lump sum credit for installing the city's pump.   $1,969.00  
76 Subtotal:       $2,350.00 $11,391.00  
77 Original Construction Bid Total ** =     $148,030.50  
78 Total Previous Change =   $0.00  
79 This Change (see itemized detail above) ** =   $2,846.77  
80 Revised Contract Total ** =   $150,877.27 1.92%
81 Original Full Completion Date =   6/30/2016    
82 ** Subject to increase or decrease in quantities per construction.      
83              
84              
85              
86              
87 Prepared by: Accepted by:      
88   Project Manager Date:   Contractor    
89              
90 Approved by:          
91   City Engineer Date:   Title   Date:
92              
93 Approved by:          
94   Public Works Director Date:        
95              
96 Approved by:          
97   City Manager Pro Tem Date:        

ChgOrdr #001

  B C D E F G
1            
2 C.O. Item # Description for
Change Order Item
Unit Estm Qnty Unit Price Subtotal
3   Underground Well No. 9  
4 1-01 Cost to change from 4 inch lateral to 6 inch, including restocking and for donuts for connecting to existing wastewater line. LS 1 2,846.77 $ 2,846.77
5  
Total =
      $ 2,846.77
6            
7            
8            
9            
10            
11            
12            
13            
14 C.O. Item # Description for
Change Order Item
Unit Estm Qnty Unit Price Subtotal
15   Underground Well No. 9  
16 1-02 (a) Provide cable extension for the existing pump. LF 120 15.00 $ 1,800.00
17   (b) Provide splice kit and labor for the existing pump. LS 1 550.00 $ 550.00
18   Total =       $ 2,350.00
19            
20            
21            
22            
23            
24            
25            
26 C.O. Item # Description for
Change Order Item
Unit Estm Qnty Unit Price Subtotal
27   Underground Well No. 9  
28 1-03 (a) Credit for using the city's pump instead of furnishing and installing the contractor's test pump for aquifer testing (relates to item #8 in the bid schedule). LS 1 (6,263.00) $ (6,263.00)
29   (b) Credit for using the city's pump to perform test pumping (relates to item #9 in the bid schedule). HR 56 (39.00) $ (2,184.00)
30   (c) Credit for setting one pump (relates to item #21 in the bid schedule). LS 1 (1,969.00) $ (1,969.00)
31   Total =       $ (10,416.00)

Change Order Item Details