| MEMORANDUM |
ENGINEERING SERVICES DEPARTMENT P.O. Box 970 · 414 E. First Street · Newberg, Oregon 97132 · Tel 503.537.1240 |
TO: Jacque M. Betz, City Manager
THRU: Gerald Fisher, Interim City Engineer, and Jay Harris, Public Works Director
FROM: Paul Chiu, Senior Engineer/Project Manager
SUBJECT: VILLA ROAD PAVEMENT STRIPING RESTORATION
Requisition Request
DATE: October 6, 2014
Background Information:
The city’s contractor, Knife River Corporation-Northwest has completed the Villa Road pavement restoration work. Their contract did not include the work for pavement striping and marking. City staff requested four pavement striping and marking contractors for price quotes and received one quote (at $7,970.00) from Specialized Pavement Marking, Inc. on September 30, 2014.
The work will be paid for through account #18-5150-702171. The approved current fiscal budget has $120,000.00 for pavement restoration and related work for N. Villa Road and N. Springbrook Road.
N. Villa Road pavement restoration (Knife River’s contract) = $91,995.60
N. Springbrook Road pavement and base repair (Raugust’s contract) = $21,470.00
N. Villa Road pavement striping restoration (Specialized Pavement Marking’s price) = $7,970.00
Total = $121,435.60
This project will be funded through the transfer of expenditures within Fund 18.
Action Request:
Please sign the request finance requisition and return both to me after signing. If you have any questions, please feel free to ask me. Thank you.