From: ORR Jim * DEQ
Sent: Wed Sep 27 09:58:35 2023
To: Lynn Green
Cc: Tori Bennett; LACEY David J * DEQ; Evan Bruggeman; ROMERO Mike * DEQ; SEIDEL Paul * DEQ; ORR Jim * DEQ; ORR Jim * DEQ
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Importance: Normal
Lynn,
I agree that the 2011 Agreement does not cover a complete groundwater pathway evaluation for source control, which was based on the CSM at the time.
DEQ has requested that the site evaluate the groundwater pathway related to source control in our attached November 29, 2022 letter, based on the results of the groundwater samples reported in the Stormwater SCE. Additionally, groundwater data collected down gradient of the Lampros Sit, as part of the RM 3.5 Project Are, reported detections of contaminants above Portland Harbor Cleanup Levels.
Due to DEQ's concerns for the groundwater pathway to the new and historic stormwater lines and the potential for direct discharge of contaminated groundwater to the river, DEQ has requested an evaluation of the groundwater pathway.
Please consider a response to our request and let me know how you will proceed.
Thank you
Jim
From: Lynn Green <lynng@evren-nw.com>
Sent: Tuesday, September 26, 2023 6:33 AM
To: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Cc: Tori Bennett <torib@evren-nw.com>; LACEY David J * DEQ <David.J.LACEY@deq.oregon.gov>; Evan Bruggeman <evanb@evren-nw.com>; ROMERO Mike * DEQ <Mike.ROMERO@deq.oregon.gov>
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Jim, I may be mistaken, but it is my interpretation of the VCP (attached) that only ground water infiltrating into the storm water system needed to be assessed. With the new storm water system, this no longer occurs. Let me know your thoughts. Thanks, Jim! Lynn
Lynn D. Green, Ph. D.
P.G.(AZ, ID, LA)/R.G. (OR)/L.G. (WA)/C.E.G. (OR)/L.E.G. (WA)/CWRE (OR)/CESCL (OR, WA)
Principal Engineering Geologist / Hydrologist
EVREN Northwest, Inc
Environmental and Natural Resource Consulting
><))))º>b ><))))º>b ><))))º> b><))))º>
From: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Sent: Monday, September 25, 2023 6:35 PM
To: Lynn Green <lynng@evren-nw.com>
Cc: Barbara Roland <broland@evren-nw.com>; Leslye Moffat-Pena <LeslyeMP@evren-nw.com>; LACEY David J * DEQ <David.J.LACEY@deq.oregon.gov>; Evan Bruggeman <evanb@evren-nw.com>; ROMERO Mike * DEQ <Mike.ROMERO@deq.oregon.gov>; ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>; ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Lynn,
DEQ provided the attached request to evaluate groundwater as it relates to source control.
Please address the request.
Thank you
Jim
From: Lynn Green <lynng@evren-nw.com>
Sent: Monday, September 25, 2023 2:54 PM
To: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Cc: Barbara Roland <broland@evren-nw.com>; Leslye Moffat-Pena <LeslyeMP@evren-nw.com>; Evan Bruggeman <evanb@evren-nw.com>
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Jim, perhaps we can discuss over the phone if necessary, but I was under the understanding that if ground water was not discharging into the storm water system that ground water assessment was not required? That was my interpretation of the VCP. Currently, ground water does not infiltrate into the new storm water system. Can you confirm if this is the case? Let me know if we need to discuss this further. Thanks, Jim! Lynn
Lynn D. Green, Ph. D.
P.G.(AZ, ID, LA)/R.G. (OR)/L.G. (WA)/C.E.G. (OR)/L.E.G. (WA)/CWRE (OR)/CESCL (OR, WA)
Principal Engineering Geologist / Hydrologist
EVREN Northwest, Inc
Environmental and Natural Resource Consulting
><))))º>b ><))))º>b ><))))º> b><))))º>
From: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Sent: Monday, September 25, 2023 7:59 AM
To: Lynn Green <lynng@evren-nw.com>; ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Cc: Barbara Roland <broland@evren-nw.com>; Leslye Moffat-Pena <LeslyeMP@evren-nw.com>; Evan Bruggeman <evanb@evren-nw.com>; ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Lynn,
Do you have an update for delivery to DEQ the SCE as it Relates to Groundwater work plan?
Thank you
Jim
From: Lynn Green <lynng@evren-nw.com>
Sent: Tuesday, April 4, 2023 9:23 AM
To: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Cc: Barbara Roland <broland@evren-nw.com>; Leslye Moffat-Pena <LeslyeMP@evren-nw.com>; Evan Bruggeman <evanb@evren-nw.com>
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Jim, attached is a summary of 1st Quarter 2023 activities at this site. The Johnson/Lampros Warehouse now has a full storm-water monitoring waiver, highlighting how effective the new storm water system is at this facility. Let me know if you have any questions related to this update. Our office will mail a hardcopy of this letter to your attention later this week. Thanks, Jim! Lynn
Lynn D. Green, Ph. D.
P.G.(AZ, ID, LA)/R.G. (OR)/L.G. (WA)/C.E.G. (OR)/L.E.G. (WA)/CWRE (OR)/CESCL (OR, WA)
Principal Engineering Geologist / Hydrologist
EVREN Northwest, Inc
Environmental and Natural Resource Consulting
><))))º>b ><))))º>b ><))))º> b><))))º>
From: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Sent: Monday, April 3, 2023 10:22 AM
To: Lynn Green <lynng@evren-nw.com>
Subject: Re: Johnson-Lampros Warehouse SCE Quarterly update
Thanks
Sent via the Samsung Galaxy S20 FE 5G, an AT&T 5G smartphone
From: Lynn Green <lynng@evren-nw.com>
Sent: Monday, April 3, 2023 10:20:32 AM
To: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Hey Jim, sorry for the delay in getting back to you. They are still reviewing insurance to see if that may be a possible way to pay for this work, as well as the agreement with the State. Hope to have an update for you later this month. FYI.
Lynn D. Green, Ph. D.
P.G.(AZ, ID, LA)/R.G. (OR)/L.G. (WA)/C.E.G. (OR)/L.E.G. (WA)/CWRE (OR)/CESCL (OR, WA)
Principal Engineering Geologist / Hydrologist
EVREN Northwest, Inc
Environmental and Natural Resource Consulting
><))))º>b ><))))º>b ><))))º> b><))))º>
From: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Sent: Thursday, March 30, 2023 9:34 AM
To: Lynn Green <lynng@evren-nw.com>
Cc: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: Johnson-Lampros Warehouse SCE Quarterly update
Hi Lynn,
Does you and you client have a response to DEQ’s request for groundwater evaluations as it related to SC?
When may I expect your response?
Thank you
Jim
From: Lynn Green <lynng@evren-nw.com>
Sent: Wednesday, January 4, 2023 4:19 PM
To: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: Johnson-Lampros Warehouse SCE Quarterly update
Jim, attached is the 4th quarter update related to SCE at the Johnson-Lampros Warehouse property. A hardcopy is being mailed to you later this week. Let me know if you have any questions. Thanks!
Lynn D. Green, Ph. D.
P.G./R.G./L.G./C.E.G./L.E.G.
Principal Engineering Geologist / Hydrologist
EVREN Northwest, Inc
Environmental and Natural Resource Consulting
><))))º>b ><))))º>b ><))))º> b><))))º>
From: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Sent: Tuesday, December 27, 2022 9:41 AM
To: Lynn Green <lynng@evren-nw.com>
Cc: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: DEQ Comments for Lampros Work Plan for SCE as it Relates to Groundwater
Sorry Lynn,
Jim
From: Lynn Green <lynng@evren-nw.com>
Sent: Tuesday, December 27, 2022 9:35 AM
To: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: DEQ Comments for Lampros Work Plan for SCE as it Relates to Groundwater
That was for the Irwin Hodson site, not this one. Scott is not involved with Lampros.
Lynn D. Green, Ph. D.
P.G./R.G./L.G./C.E.G./L.E.G.
Principal Engineering Geologist / Hydrologist
EVREN Northwest, Inc
Environmental and Natural Resource Consulting
><))))º>b ><))))º>b ><))))º> b><))))º>
From: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Sent: Tuesday, December 27, 2022 9:34 AM
To: Lynn Green <lynng@evren-nw.com>
Cc: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: DEQ Comments for Lampros Work Plan for SCE as it Relates to Groundwater
Hi Lynn
Scot responded.
There is a question regarding the stamping of the letter.
Thank you
Jim
From: Lynn Green <lynng@evren-nw.com>
Sent: Tuesday, December 27, 2022 9:32 AM
To: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>; 'James Johnson' <james@peniron.com>
Cc: 'Marcus Lampros - Lampros Steel (Lamprosmarcus@gmail.com)' <lamprosmarcus@gmail.com>; 'Hanna, Laura' <Hanna.Laura@epa.gov>; ROMERO Mike * DEQ <Mike.ROMERO@deq.oregon.gov>; LACEY David J * DEQ <David.J.LACEY@deq.oregon.gov>; SEIDEL Paul * DEQ <Paul.SEIDEL@deq.oregon.gov>; 'Dave Johnson' <dave@peniron.com>
Subject: RE: DEQ Comments for Lampros Work Plan for SCE as it Relates to Groundwater
Thanks, Jim. We plan to discuss next week, as many folks are AN due to the holidays, and get back to you with any questions or responses, as applicable, along with timelines. Thanks again, Jim!
Lynn D. Green, Ph. D.
P.G./R.G./L.G./C.E.G./L.E.G.
Principal Engineering Geologist / Hydrologist
EVREN Northwest, Inc
Environmental and Natural Resource Consulting
><))))º>b ><))))º>b ><))))º> b><))))º>
From: ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Sent: Tuesday, December 27, 2022 8:55 AM
To: 'James Johnson' <james@peniron.com>
Cc: 'Marcus Lampros - Lampros Steel (Lamprosmarcus@gmail.com)' <lamprosmarcus@gmail.com>; 'Hanna, Laura' <Hanna.Laura@epa.gov>; ROMERO Mike * DEQ <Mike.ROMERO@deq.oregon.gov>; LACEY David J * DEQ <David.J.LACEY@deq.oregon.gov>; SEIDEL Paul * DEQ <Paul.SEIDEL@deq.oregon.gov>; Lynn Green <lynng@evren-nw.com>; 'Dave Johnson' <dave@peniron.com>; ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: RE: DEQ Comments for Lampros Work Plan for SCE as it Relates to Groundwater
Lampros Team,
When should I expect your response to our comments for the SCE as it relates to the Groundwater work plan?
Thank you
Jim
From: ORR Jim * DEQ
Sent: Tuesday, November 29, 2022 10:02 AM
To: James Johnson <james@peniron.com>
Cc: Marcus Lampros - Lampros Steel (Lamprosmarcus@gmail.com) <lamprosmarcus@gmail.com>; Hanna, Laura <Hanna.Laura@epa.gov>; ROMERO Mike * DEQ <Mike.ROMERO@deq.oregon.gov>; LACEY David J * DEQ <David.J.LACEY@deq.oregon.gov>; SEIDEL Paul * DEQ <Paul.SEIDEL@deq.oregon.gov>; Lynn Green <lynng@evren-nw.com>; Dave Johnson <dave@peniron.com>; ORR Jim * DEQ <Jim.ORR@deq.oregon.gov>
Subject: DEQ Comments for Lampros Work Plan for SCE as it Relates to Groundwater
Please let me know if there are questions.
Thank You kindly
Jim Orr R.G.
DEQ Northwest Region
700 NE Multnomah St., Suite 600
Portland, Oregon 97232
503-961-2647 Cell Phone
Useful DEQ Links:
State of Oregon: Department of Environmental Quality
Oregon DEQ: Land Quality - Environmental Cleanup Site Information (ECSI) Database