From: Andy Peters

Sent: Mon Oct 18 08:54:09 2021

To: 'PINNEY Mike * DEQ'

Subject: RE: Molalla Value Engineering Schedule coordination

Importance: Normal

 

Mike, yes, MENG Analysis will conduct the Value Engineering, here is the information:

Sarah M. Partap, MBA, VMA

Principal

MENG Analysis

2001 Western Avenue, Suite 200

Seattle, WA 98121-3300

Mobile 206-451-3462

Office: 206.838.9797

www.menganalysis.com

Independent Quality & Cost Performance Services

Value Analysis · Constructability · Cost Estimating · Commissioning · Facility Condition Assessments

-----Original Message-----

From: PINNEY Mike * DEQ <mike.pinney@deq.state.or.us>

Sent: Monday, October 18, 2021 8:52 AM

To: Andy Peters <apeters@cityofmolalla.com>

Subject: RE: Molalla Value Engineering Schedule coordination

Andy,

Who is running the Value Engineering? Are you using a professional group?

Mike

-----Original Message-----

From: Andy Peters <apeters@cityofmolalla.com>

Sent: Monday, October 18, 2021 8:36 AM

To: PINNEY Mike * DEQ <mike.pinney@deq.state.or.us>

Cc: YELTON-BRAM Tiffany <Tiffany.YELTON-BRAM@state.or.us>; RUBY Tim <Tim.RUBY@state.or.us>; Mac Corthell <mcorthell@cityofmolalla.com>; Dan Huff <dhuff@cityofmolalla.com>; S Major <smajor@dyerpart.com>

Subject: Molalla Value Engineering Schedule coordination

Good Morning Mr. Pinney, I left you a voicemail Friday but following up:

Molalla is still on track to submit its complete Pre-design Report in November, so we are preparing to schedule Value Engineering. The second Engineer will be MENG Analysis (Sarah M. Partap, Principle). Meng is working to get a proposal to us shortly, and in addition to the Dyer team, is expected to include:

1. Civil Engineer

2. Mechanical/Process Engineer

3. Construction Manager

4. Process Engineer

5. Operations/Process Engineer (Dale Richwine)

6. Contractor Cost Estimating Manager

7. Structural Engineer (by phone)

8. Geotechnical Engineer (by phone)

We would like to schedule so that DEQ can comfortably attend, and have plenty of time to review before the meetings begin. So right now the week of December 6th - 10th works for most of our Engineering teams, with the next availability being January 10-14th. Will either of these weeks work for DEQ?

Thanks very much, we're looking forward to this process with you!

Respectfully,

Andy Peters

City of Molalla

Public Works Operations Supervisor

(503) 829-6855 x220

Cell: 503-793-0507

apeters@cityofmolalla.com

117 N Molalla Ave

Molalla, OR 97038