Hi all,

Thanks again for taking the time to hop on a call this morning and discuss the Phase 2 stormwater improvements project for the Vigor Swan Island facility.

Per our discussion, I have attached the overview figure I showed in today's meeting. Additional information requests are described below.

Analytical Parameters for Stormwater:

 

SCMs in Other Basins

 

Please let me know if you have any additional questions. Thank you!