From: Leake, Benjamin

Sent: Wed Mar 30 15:07:07 2022

To: HOY Ray * DEQ

Cc: LACEY David J * DEQ

Subject: RE: Guilds Lake Yard Source Control Evaluation Addendum Report

Importance: Normal

Attachments: image001.png; 2022.03.30_Guilds Lake SCE Addendum_DRAFT EPA Comments.pdf;

 

Microsoft Exchange Server;converted from html;

Hi Ray,

I’ve attached some draft comments on the Guilds Lake SCE Addendum report. Take a look and let me know if you’d like to discuss.

Since the addendum relies on the 2013 SCE report and the 2020 Tech Memo, I’ve included some comments on those reports as well. As I state in the front matter though, I’m not asking for revisions to those documents, but wanted to highlight some shortcomings that can hopefully inform the SC work going forward.

Also, we don’t seem to have the referenced document:

Eastern System Permanent Closure Report, Guilds Lake Yard, dated August 4, 2016 prepared by Farallon

Not a big hurry, but I’d like to have that one in my site file if you have it available to share.

Thanks,

Ben

Benjamin Leake, PMP

Remedial Project Manager

U.S. Environmental Protection Agency

Region 10, Oregon Operations Office

Office: (503) 326-2859

From: HOY Ray * DEQ <ray.hoy@deq.state.or.us>

Sent: Wednesday, December 1, 2021 8:03 PM

To: Leake, Benjamin <Leake.Benjamin@epa.gov>

Cc: LACEY David J * DEQ <david.j.lacey@deq.state.or.us>

Subject: FW: Guilds Lake Yard Source Control Evaluation Addendum Report

Hi Ben,

 

I’ve attached a SC Addendum from BNSF for their Guild’s Lake Yard site. I will be reviewing it for a SC Decision in the next few months and wanted to give you a head’s up if you wanted to have input on it.

 

Happy Holidays to you and yours.

 

Ray Hoy

Ray Hoy

Oregon Department of Environmental Quality

NWR Clean-up Project Manager and Site Assessment Coordinator

700 NE Multnomah St., Suite #600

Portland, OR 97232

503 229-5069; 503 537-8718 cell

From: Stacy Patterson <spatterson@farallonconsulting.com>

Sent: Tuesday, April 6, 2021 7:25 AM

To: HOY Ray <Ray.HOY@state.or.us>

Cc: Stacy Patterson <spatterson@farallonconsulting.com>; Mark B. Havighorst <mhavighorst@farallonconsulting.com>; Hibbs, Ryan Edward <Ryan.Hibbs@BNSF.com>; DeGross, Shane <Shane.Degross@BNSF.com>; Terry D. Brown <TDBROWN@UP.COM>; Robert B. Lowry <RLowry@kelrun.com>; Kate L. Moore <KMoore@dunncarney.com>

Subject: Guilds Lake Yard Source Control Evaluation Addendum Report

Hello Ray,

Farallon Consulting, L.L.C on behalf of the Portland Terminal Railway Company and the BNSF Railway Company is providing the Guilds Lake Yard Source Control Evaluation Addendum Report (SCE Addendum). The SCE Addendum can be downloaded from the link below. Please let me know if you have any issues downloading the document and please reach out to me with any questions regarding the SCE Addendum.

https://farallon.egnyte.com/fl/WZvPFNN0bL

Thank you, Stacy Patterson

Stacy D. Patterson, Principal Environmental Scientist

Farallon Consulting | 975 5th Ave Northwest | Issaquah, WA 98027

D: 425-295-0812 Currently working from home: 425-466-1121 |Bio | LinkedIn

image

This correspondence contains confidential or privileged information from Farallon Consulting and may be "Attorney-Client Privileged" and protected as "Work Product." The information contained herein is intended for the use of the individual or party named above. If you are not the intended recipient, note that any copying, distribution, disclosure, or use of the text and/or attached document(s) is strictly prohibited. If you have received this correspondence in error, please notify us immediately. Thank you.