Heintz Street is still in a moratorium but there are provisions for allowing a cut into the pavement. Per our Public Works Standards:
2.7.3 Asphalt Restoration for Streets Listed on 5-Year Moratorium
When emergencies or special circumstances require access to underground utilities, the City may allow street cuts in streets listed on the 5-year moratorium (see Subsection 2.2.34, “Utilities”). In addition to the repair work outlined in Subsection 2.7.2, “Asphalt Concrete Replacement,” an additional mill and inlay shall be required over the repaired area to a point 1-foot beyond the T-cut perimeter.
This section of roadway is about 5” thick. We will require that a 1-foot tee cut be done and install 3” of Level 2, ½” HMAC followed by a 1-foot grind and 2” inlay to seal the roadway. The edges must be tacked and the top joint must be sand sealed. The patch must be completed on the same day and the top lift will be in one continuous paving operation so there are no cold joints.
Sam is our new Sr. Engineering Tech and will be inspecting the paving operations. Let Sam and I know which alternative you want to go with (bore or cut) and then we can discuss schedule. Paving is dependent upon weather and needs to be done before the end of October.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Travis Edge <Tedge@wavebroadband.com>
Sent: Tuesday, September 17, 2019 12:25 PM
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: RE: AT&T/DSR – US Bank Undergound – 415 Center Ave Molalla Oregon
Excellent, thank you
Travis Edge
Construction Coordinator
Construction Project Management
Wave
669 Ray J. Glatt Circle
Woodburn, OR 97071
503.899.3267 (m)
From: Gerald Fisher <gfisher@cityofmolalla.com>
Sent: Tuesday, September 17, 2019 12:16 PM
To: Travis Edge <Tedge@wavebroadband.com>
Subject: RE: AT&T/DSR – US Bank Undergound – 415 Center Ave Molalla Oregon
I need to check and make sure that street is not under moratorium. Will get back to you.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Travis Edge <Tedge@wavebroadband.com>
Sent: Tuesday, September 17, 2019 11:18 AM
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: AT&T/DSR – US Bank Undergound – 415 Center Ave Molalla Oregon
Hi Gerald
Jaison Krueger, our Wave Permit guy has contacted you for permits recently and I am bugging you with a question… Thanks in advance for your time.
At the corner of Center Ave & E Heintz st. there is many utilities that our contractor(Mt. West Util) is concerned about crossing plus the high pressure gas main.
Is there possibility we can open cut the asphalt for our road crossing??