From: Darin Vess

Sent: Thu Feb 06 15:26:00 2020

To: Sam Miller; Brian Baune

Cc: Gerald Fisher

Subject: RE: M2760479 Christopher St. PW63-2019

Importance: Normal

 

Good Afternoon Sam,

I am adding our CSI for PGE to this email string, he will have a better idea of completion. I know Kuenzi has been waiting for better weather for the hard surface repairs.

Thanks,

Darin

From: Sam Miller <smiller@cityofmolalla.com>

Sent: Thursday, February 6, 2020 2:35 PM

To: Darin Vess <darin.vess@pgn.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: RE: M2760479 Christopher St. PW63-2019

***Please take care when opening links, attachments or responding to this email as it originated outside of PGE.***


 

Good Afternoon Darin,

Can you give me an update on Christopher St. permit M2760479 on abandoned Power Pole removal at 329 Christopher St., Asphalt with sand seal on all open trenches and landscaping touch up. Thanks.

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: Darin Vess <darin.vess@pgn.com>

Sent: Wednesday, January 15, 2020 8:50 AM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: RE: M2760479 Christopher St. PW63-2019

Pre-Coord just sent me the file.

Thanks.

From: Darin Vess

Sent: Wednesday, January 15, 2020 8:49 AM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: RE: M2760479 Christopher St. PW63-2019

Good Morning Sam,

The attached file didn’t come through, want you to know.

Thanks,

Darin

From: Sam Miller <smiller@cityofmolalla.com>

Sent: Wednesday, January 15, 2020 8:45 AM

To: Darin Vess <darin.vess@pgn.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: M2760479 Christopher St. PW63-2019

***Please take care when opening links, attachments or responding to this email as it originated outside of PGE.***


 

Good Morning Darin

Please see attach file for easement right away demotions. The Public Work Director has advised me that the City of Molalla will not allow power to be placed in the street. There is a 7’ right of way easement from back of curb on Christopher St., which allow all utility to be placed. The City does allow street crossing. Please direct crew to relocate power into the easement. Placement of the vault needs to have a 1% slope from back of curb for future sidewalk development. Please let me know if you have any question or concerns.

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038