From: Sam Miller
Sent: Tue Apr 07 15:01:34 2020
To: Russell Dodge
Cc: Gerald Fisher; Alice Cannon; Dan Zinder
Subject: RE: Fenton Avenue - PGE Poles
Importance: Normal
Attachments: SN2019-221.tif; SN2019-174.tif; image001.jpg; Hello Russell, See attached per and post construction record of survey maps of Fenton Ave. showing a 50’ right-of-way in relation to the property line. Back of sidewalk should be back of right-of-way. As to showing the future sidewalk, The City doesn’t have a design set of plans at this time. Gerald Fisher our Public Works Director can give more of a definitive answer to the sidewalk location, He will be out of the office until Monday the 13th. Let me know if this helps. Regards, Sam Miller | Sr. Engineer Tech. City of Molalla 117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038 T : 503-759-0217 | E: smiller@cityofmolalla.com From: Russell Dodge <Russell.Dodge@pgn.com> Sent: Tuesday, April 7, 2020 12:49 PM To: Sam Miller <smiller@cityofmolalla.com> Cc: Gerald Fisher <gfisher@cityofmolalla.com>; Alice Cannon <acannon@cityofmolalla.com>; Dan Zinder <dzinder@cityofmolalla.com> Subject: RE: Fenton Avenue - PGE Poles Thanks for the quick reply Sam. Looking at the as-built I can’t find any sidewalk in relation to the right-of-way. I’ve been told there is going to be a sidewalk installed along Fenton Ave. Is there anything that shows the future sidewalk? Thanks for your help! Russell Dodge LSIT | Surveyor Portland General Electric 121 SW Salmon St, Portland, OR 97204 Office: 503.464.8148 Cell: 503.715.7973 From: Sam Miller <smiller@cityofmolalla.com> Sent: Tuesday, April 7, 2020 12:09 PM To: Russell Dodge <Russell.Dodge@pgn.com> Cc: Gerald Fisher <gfisher@cityofmolalla.com>; Alice Cannon <acannon@cityofmolalla.com>; Dan Zinder <dzinder@cityofmolalla.com> Subject: RE: Fenton Avenue - PGE Poles ***Please take care when opening links, attachments or responding to this email as it originated outside of PGE.***
Good Afternoon Russell,
See attached as-builts for Fenton Ave. Let me know if this will work or if you have any more question. Thanks.
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: Russell Dodge <Russell.Dodge@pgn.com>
Sent: Tuesday, April 7, 2020 11:22 AM
To: Sam Miller <smiller@cityofmolalla.com>
Subject: Fenton Avenue - PGE Poles
Hello Sam,
I’m with the Portland General Electric Land Survey department. I previously emailed the City of Molalla Planning department but after some more digging I found you may be more helpful. I’m aware that there is going to be a widening along Fenton Avenue. We are looking to relocate our poles so they are behind the sidewalk but within the right-of-way. I don’t have anything to show me where the back of walk is going to end up. Are there any plans you can send me for this? We’re going to send a survey crew this week or next week to pick up right-of-way and existing conditions hopefully.
Thanks!
| Russell Dodge LSIT | Surveyor Portland General Electric 121 SW Salmon St, Portland, OR 97204 Office: 503.464.8148 Cell: 503.715.7973 |