From: Melissa Griffith
Sent: Tue Oct 08 15:19:09 2019
To: Gerald Fisher
Subject: RE: PGE work notice
Importance: Normal
Hi Gerald,
PGE will be back on site Wednesday, October 9, 2019 to finish this job at 809 Meadow Dr.
PGE job M2742412
City of Molalla permit 31-2019
Thank you
Melissa Griffith
Resource Scheduler – Southern Districts
10800 SW Avery St., Tualatin, OR 97062
503-612-2908
From: Gerald Fisher <gfisher@cityofmolalla.com>
Sent: Thursday, October 3, 2019 12:29 PM
To: Melissa Griffith <Melissa.Griffith@pgn.com>
Subject: RE: PGE work notice
***Please take care when opening links, attachments or responding to this email as it originated outside of PGE.***
Thanks Melissa. I let our folks know.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Melissa Griffith <Melissa.Griffith@pgn.com>
Sent: Thursday, October 3, 2019 11:48 AM
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: PGE work notice
Good Afternoon,
PGE crews will be working on Monday, October 7, 2019 at 809 Meadow Dr Molalla to replace a streetlight pole.
PGE job M2742412
City of Molalla permit 31-2019
Thank you
Melissa Griffith
Resource Scheduler – Southern Districts
10800 SW Avery St., Tualatin, OR 97062
503-612-2908