From: Andy Peters

Sent: Thu Aug 23 10:14:06 2018

To: Dan Huff

Cc: Gerald Fisher

Subject: HVAC Upstairs

Importance: Normal

 

Dan, Gerald asked me to get you the information on HVAC improvements upstairs requested by the PD. I have a PO cocked and can probably have this done in less than a month, it’s a “no big deal” project. Here is the info:

Project Name: City Hall Upstairs HVAC Improvements

Total Cost: $13,769

Scope of Work:

-There will be a single RUUD Mini Split 4.5 ton outdoor unit installed on ground, the North side of City Hall

-Permits, electrical and drain plumbing included

-Five Indoor wall mounted air handle units will be installed, locations were specified by the Police Chief:

2x in evidence room

1x in records room

1x in judges office

1x in Detective's office

Procurement:

This is an intermediate procurement (ORS 279B.070), 3 quotes. I reached out to 4 companies and met with three of them on site.

-Evergreen: elected to not bid

-Oregon Ductless: $13,769, including electrical

-Jet Industries: $19,500 excluding electrical.

-Pyramid: Elected to not bid

Thank you!

Andy Peters

City of Molalla

Public Works Operations Supervisor

(503) 829-6855 x220

Cell: 503-793-0507