From: Jennifer Cline
Sent: Thu Feb 26 14:11:26 2015
To: hai@curran-mcleod.com
Cc: Heather Penni
Subject: RE: Stowers Road Grange Ave. and Heintz St
Importance: Normal
Hi Hassan,
It will have to be sometime tomorrow for me. Do you want to meet here at City Hall? I don’t mind paying for underground utility conflicts as long as they itemize the work (i.e. location(station), labor, time and materials)
I don’t agree with lump sum payments without back up information, this does not provide transparency for the City.
Thank you,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Thursday, February 26, 2015 1:06 PM
To: jcline@cityofmolalla.com
Cc: 'Curtis Cooksey'
Subject: RE: Stowers Road Grange Ave. and Heintz St
Hi Jenn,
I have seen three change order requests regarding the waterline so far, I think we need to get together with Eagle-Elsner and resolve. The only thing I don’t understand is why we have a three man crew and dump trucks waiting around the whole 8 hour shift, could have anything else on the project be done?
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Thursday, February 26, 2015 12:27 PM
Subject: Stowers Road Grange Ave. and Heintz St
Hi Hassan,
The Pipe Crew hit a 12” storm line that was not on the plans and we could not locate it since it was concrete.
The City supplied us with the pipe, we had to buy 2 concrete to PVC fernco’s.
Curtis