From: Hassan Ibrahim

Sent: Wed Jan 07 07:46:17 2015

To: 'Jennifer Cline'

Subject: RE: Stowers Road, Heintz & Grange Impprovements

Importance: Normal

 

Yes.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, January 07, 2015 7:28 AM

To: hai@curran-mcleod.com

Subject: RE: Stowers Road, Heintz & Grange Impprovements

Me too.

Okay, will 9 AM work then?

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Wednesday, January 07, 2015 7:28 AM

To: 'Jennifer Cline'

Subject: RE: Stowers Road, Heintz & Grange Impprovements

I am leaving the office at noon on Friday, so discussing before 11:30 works good.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, January 07, 2015 7:22 AM

To: hai@curran-mcleod.com

Subject: RE: Stowers Road, Heintz & Grange Impprovements

It won’t be a delay if it’s whether related.

However according to the 2008 ODOT specs Section 00745.40 after March 15th thru Sept 30 we can allow paving above 45-deg for 2” and above given the pavement surface is dry. I would like to see the final lift of paving done at one time however for better quality control.

I’m still working through some specifics, can we discuss the draft Friday morning before 11:30? I will do my best to get a copy to you by noon tomorrow or sooner.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Wednesday, January 07, 2015 6:23 AM

To: 'Jennifer Cline'

Cc: 'Dan Huff'; 'Garrett Edmunds'

Subject: RE: Stowers Road, Heintz & Grange Impprovements

Hi Jen,

Let’s discuss all the details/ concerns at the preconstruction meeting. With only 60 days contract time and unless there are technical concerns, I would like to turn them loose and hate to slow them down and be held responsible for delays.

Regards,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Tuesday, January 06, 2015 3:59 PM

To: hai@curran-mcleod.com

Cc: Dan Huff; Garrett Edmunds

Subject: RE: Stowers Road, Heintz & Grange Impprovements

Hi Hassan,

Looking at their attached schedule, I’m going to request to hold off on adjusting utilities and all final paving for all streets until at least April-May for temperature and weather restrictions. All final lifts or overlays can be done at one time in good weather. I would also recommend limiting full roadway reconstruction on Stowers until after April. That area of town has a high water table with drainage issues. The contractor most likely will have a hard time reaching compaction on the sub-grade without digging out soft spots.

Pavement Repair and temporary utility patches can be done prior.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Tuesday, January 06, 2015 11:13 AM

To: 'Jennifer Cline'

Subject: FW: Stowers Road, Heintz & Grange Impprovements

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Tuesday, January 06, 2015 11:05 AM

To: hai@curran-mcleod.com

Subject: Stowers Road, Heintz & Grange Impprovements

Hi Hassan,

I’m sending you the project schedule and a three week schedule that Mike will fill out on site every week.

Thanks

Curtis