From: Curtis Cooksey
Sent: Wed Feb 04 07:52:06 2015
To: hai@curran-mcleod.com
Cc: jcline@cityofmolalla.com
Subject: RE: Stowers Rd. Waterline Replacement
Importance: Normal
Hi Hassan,
I will contact the supplier on when the parts can be delivered.
Curtis
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Wednesday, February 04, 2015 6:52 AM
To: Curtis Cooksey
Cc: 'Garrett Edmunds'; 'Jennifer Cline'
Subject: RE: Stowers Rd. Waterline Replacement
Hi Curtis,
Please see below the response from Jennifer and can you tell us what is the time delay on waterline material delivery?
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, February 03, 2015 1:08 PM
To: Hassan Ibrahim
Cc: Garrett Edmunds
Subject: Stowers Rd. Waterline Replacement
Hi Hassan,
Please confirm the delay of expected delivery of the water line materials.
I would like to proceed with the replacement of the Stowers Rd. waterline. We most likely will need to give the contractor a delay for procurement of materials on the Stowers Rd. portion of work only.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676