From: Hassan Ibrahim

Sent: Thu Apr 30 05:52:52 2015

To: 'Jennifer Cline'; 'Curtis Cooksey'

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Importance: Normal

Attachments: image001.jpg;

 

ODOT allows placement a week after paving.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, April 29, 2015 5:37 PM

To: Curtis Cooksey

Cc: Hassan Ibrahim

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Thermoplastic typically cannot be placed for ~40 day after paving. I will have to look up the ODOT spec to see if there are restrictions.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Wednesday, April 29, 2015 1:16 PM

To: jcline@cityofmolalla.com

Subject: FW: Stowers Rd, Heintz St. and Grange Ave.

Hi Jennifer,

Just FYI

Curtis

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Wednesday, April 29, 2015 11:34 AM

To: Curtis Cooksey

Cc: MikeZiegler@spmnw.com

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Hi Curtis,

All the striping on this project will be thermoplastic as per section 02500-2.07 of the spec’s. “Painted striping or legends will not be permitted”.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Wednesday, April 29, 2015 11:18 AM

To: hai@curran-mcleod.com

Cc: mailto:MikeZiegler@spmnw.com

Subject: FW: Stowers Rd, Heintz St. and Grange Ave.

Hi Hassan,

Could you answer this?

Thanks!

Curtis

From: Candice Tavernier [mailto:Candice@spmnw.com]

Sent: Wednesday, April 29, 2015 10:51 AM

To: Curtis Cooksey

Cc: Mike Ziegler

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Curtis –

In regards to submittals for this project:

Item B-12: Permaline Thermoplastic , as per spec.

Item B-13 & B-14: There is no reference to a spec or required product for these items. So, typically we would submit paint (which I am), but I’m also submitting as an alternate a high skid thermoplastic Type A-HS. Please let us know if the City would like to go with paint or thermo for these items so we can schedule accordingly.

Let me know if you have any questions.

Thanks,

Candice Tavernier

Contract Administrator

Specialized Pavement Marking, Inc.

image

P: (503) 885-0420

F: (503) 582-8629

candice@spmnw.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Monday, April 20, 2015 1:57 PM

To: Candice Tavernier

Subject: Stowers Rd, Heintz St. and Grange Ave.

Hi Candice,

Here you go.

Thanks

Curtis