From: Curtis Cooksey

Sent: Thu Apr 30 14:56:44 2015

To: hai@curran-mcleod.com

Cc: jcline@cityofmolalla.com

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Importance: Normal

Attachments: image001.jpg;

 

Hi Hassan,

It sounds like we will finish the asphalt today on Stowers, I have the pavement markings scheduled for next Tuesday, that will give us 5 days of cure time on Stowers , 8 days on Grange and 6 days on Heintz.

Let me know if I need to hold off on the pavement markings for longer cure time.

Also Dave said he has a couple of driveways to do tomorrow and a patch on Heintz then he will be done with the paving.

Since the crew is still on site I would like to request a punch list.

Thanks

Curtis

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Thursday, April 30, 2015 8:12 AM

To: Curtis Cooksey

Cc: jcline@cityofmolalla.com

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Hi Curtis,

I don’t have any concerns with this submittal.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Thursday, April 30, 2015 8:07 AM

To: hai@curran-mcleod.com

Cc: jcline@cityofmolalla.com

Subject: FW: Stowers Rd, Heintz St. and Grange Ave.

Hi Hassan,

FYI

Curtis

From: Candice Tavernier [mailto:Candice@spmnw.com]

Sent: Thursday, April 30, 2015 8:05 AM

To: Curtis Cooksey

Cc: Mike Ziegler

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Curtis –

I apologize for the confusion on our end, looks as though we were missing some key information form the bid packet. Anyways, attached is a revised submittal package - We will be using Type A Thermo for all the bid items.

Let me know if you have any questions.

Thank you,

Candice Tavernier

Contract Administrator

Specialized Pavement Marking, Inc.

image

P: (503) 885-0420

F: (503) 582-8629

candice@spmnw.com

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Wednesday, April 29, 2015 11:34 AM

To: 'Curtis Cooksey'

Cc: Mike Ziegler

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Hi Curtis,

All the striping on this project will be thermoplastic as per section 02500-2.07 of the spec’s. “Painted striping or legends will not be permitted”.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Wednesday, April 29, 2015 11:18 AM

To: hai@curran-mcleod.com

Cc: mailto:MikeZiegler@spmnw.com

Subject: FW: Stowers Rd, Heintz St. and Grange Ave.

Hi Hassan,

Could you answer this?

Thanks!

Curtis

From: Candice Tavernier [mailto:Candice@spmnw.com]

Sent: Wednesday, April 29, 2015 10:51 AM

To: Curtis Cooksey

Cc: Mike Ziegler

Subject: RE: Stowers Rd, Heintz St. and Grange Ave.

Curtis –

In regards to submittals for this project:

Item B-12: Permaline Thermoplastic , as per spec.

Item B-13 & B-14: There is no reference to a spec or required product for these items. So, typically we would submit paint (which I am), but I’m also submitting as an alternate a high skid thermoplastic Type A-HS. Please let us know if the City would like to go with paint or thermo for these items so we can schedule accordingly.

Let me know if you have any questions.

Thanks,

Candice Tavernier

Contract Administrator

Specialized Pavement Marking, Inc.

image

P: (503) 885-0420

F: (503) 582-8629

candice@spmnw.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Monday, April 20, 2015 1:57 PM

To: Candice Tavernier

Subject: Stowers Rd, Heintz St. and Grange Ave.

Hi Candice,

Here you go.

Thanks

Curtis