From: Hassan Ibrahim

Sent: Mon May 11 12:33:25 2015

To: jcline@cityofmolalla.com

Cc: 'Curtis Cooksey'

Subject: RE: Stowers Rd, Heintz St. & Grange Ave.

Importance: Normal

Attachments: Eagle_Elsner002.pdf;

 

Hi Jen,

What are your thoughts on this?

The additional 11 lf of 10” DI storm pipe replacement on Stowers,

There is also 23 lf of curb removal and replacement at one of the residents driveway on Stowers?

You have already authorized raising the manholes $1,174.00

You have also authorized replacing the stove pipe between the catchbasin $1,608.00

The asphalt grinding cost needs to be resolved as well.

Please let me know how to proceed and I hope that is all there is out there.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Monday, May 11, 2015 12:10 PM

To: hai@curran-mcleod.com

Cc: jcline@cityofmolalla.com

Subject: FW: Stowers Rd, Heintz St. & Grange Ave.

Hassan,

Eagle-Elsner was asked to fix this leak, it was on the opposite side of the road that we did our work on.

Apparently it wasn’t noticed leaking until the grinder milled the asphalt out. Since it was on the opposite of the road, Eagle-Elsner feels we are not responsible for it.

Curtis

From: Curtis Cooksey

Sent: Saturday, May 02, 2015 10:03 AM

To: hai@curran-mcleod.com

Cc: jcline@cityofmolalla.com

Subject: Stowers Rd, Heintz St. & Grange Ave.

Hi Hassan,

I’m sending you the cost to fix the existing water line leak.

Curtis