Hi Curtis,
Can you send us a schedule showing how you will be meeting the contract timelines listed below?
Thanks,
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Thursday, March 19, 2015 6:40 AM
To: 'Curtis Cooksey'
Cc: 'Jennifer Cline'
Subject: RE: Stowers Rd. Grange Ave. & Heintz Street
Hi Curtis,
I looked at the contract timelines and it appears substantial completion must be achieved on April 18 and final completion on May 18.