From: Hassan Ibrahim

Sent: Mon Jan 05 10:26:50 2015

To: SHOEMAKER Justin D

Cc: 'Jennifer Cline'; Curtis Cooksey

Subject: RE: Stowers, Heintz & Grange - Preconstruction Meeting

Importance: Normal

 

Hi Justin,

You have indicated that you want to be present at the preconstruction meeting, below are the proposed dates from the City, Can you make any of those dates?

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Tuesday, December 30, 2014 5:27 PM

To: Hassan Ibrahim

Cc: Dan Huff; Garrett Edmunds

Subject: Stowers, Heintz & Grange - Preconstruction Meeting

Hi Hassan,

Here are the following times we have available to meet for a Pre-construction meeting, please let me know what works best for your and the contractors schedule:

1/8/15 – Thursday – 2 PM

1/9/15 – Friday – 10 AM

1/13/15 – Tuesday – 10 AM

Regarding the contracts, Dan has signed the 3 copies. The bond and power of attorney dates were not added at this time in case they need to be witnessed by the notary. When completed the City would like 1 additional copy for working use.

Thank you,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C: