From: Hassan Ibrahim

Sent: Mon Mar 30 06:51:46 2015

To: 'Jennifer Cline'

Cc: 'Heather Penni'

Subject: RE: Storm on Stowers

Importance: Normal

Attachments: image001.jpg;

 

Hi Jenn,

The project Standard General Conditions, article 13.03E.1 states “the quantity of any item of unit price work performed by contractor differs materially and significantly from the estimated quantity of any such item indicated in the agreement”, let’s wait and see what the subgrade stabilization quantity turns out to be and then we can follow up on it.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, March 27, 2015 11:28 AM

To: hai@curran-mcleod.com

Cc: Heather Penni

Subject: RE: Storm on Stowers

We do not have inventory for either pipe. I will talk to Dick today to make a decision on what pipe will work best. And let you know about a change order. Also, I would like to upsize the Storm line 2” to be able to cover the change order with SDC funding if possible.

I will let you negotiate the over ex unit cost with Dick.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Friday, March 27, 2015 11:01 AM

To: 'Jennifer Cline'

Subject: RE: Storm on Stowers

As discussed on the phone, I would suggest we replace the PVC 3034 pipe with Ductile iron or PVC C900. The City crew can easily replace with that being so shallow.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, March 27, 2015 10:06 AM

To: Hassan Ibrahim

Subject: Storm on Stowers

Hi Hassan,

 

There's an issue with the storm elevation here on Stowers. You can see in the photo we have a storm line with 0.3' to go to grade for the rock. Bob is not comfortable with compacting over this w/out proper cover and I agree. Any thoughts?

 

Jenn

image

 

 

 

Sent from my iPhone