From: Hassan Ibrahim

Sent: Mon Feb 02 13:56:16 2015

To: 'Jennifer Cline'

Subject: RE: Material Submittals

Importance: Normal

 

We normally inspect the material in the field based on the approved submittals, we don’t have a tracking form but if you have a form in mind or an example and what you want to see, then I will see how to reconcile your concerns.

They will be pouring curbs on Grange tomorrow, I presume you will be looking at the string line before they pour but if you can’t, please let me know to make arrangements.

Have you decided if you want to run concrete cylinders?

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, January 30, 2015 4:42 PM

To: Hassan Ibrahim

Cc: Garrett Edmunds

Subject: Material Submittals

Hi Hassan,

Have you had a chance to make a tracking sheet for all the necessary material submittals? Is this something you do to normally track that they are submitting what they need to ahead of time?

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676