From: Jennifer Cline

Sent: Fri Jul 24 08:36:52 2015

To: Hash, Kenneth F.

Cc: Buehler, John A.

Subject: RE: Heintz Street - Submittal #7.1 - Precast Manholes Revised

Importance: Normal

Attachments: Approved_SM S-007.1_Precast Manhole Mtls.pdf;

 

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hash, Kenneth F. [mailto:HashK@hdjdg.com]

Sent: Friday, July 24, 2015 8:31 AM

To: Jenn Cline (jcline@cityofmolalla.com) <jcline@cityofmolalla.com>

Subject: FW: Heintz Street - Submittal #7.1 - Precast Manholes Revised

Ready for approval

From: Buehler, John A.

Sent: Friday, July 24, 2015 7:55 AM

To: Hash, Kenneth F. <HashK@hdjdg.com>

Subject: RE: Heintz Street - Submittal #7.1 - Precast Manholes Revised

They are good.

John A. Buehler, E.I.T. | Engineer II

HDJ DESIGN GROUP, PLLC

Engineers | Landscape Architects | Planners | Surveyors

314 W. 15th Street, Vancouver, WA 98660-2927

Phone: 360/695-3488 ext. 2107, Fax: 360/695-8767

BuehlerJ@hdjdg.com

www.hdjdg.com

From: Hash, Kenneth F.

Sent: Thursday, July 23, 2015 3:26 PM

To: Buehler, John A. <BuehlerJ@hdjdg.com>

Subject: Fwd: Heintz Street - Submittal #7.1 - Precast Manholes Revised

Please check

 

Sent from my iPhone

 

Begin forwarded message:

From: "Nick Jones" <nickj@wtc-inc.com>

To: "Hash, Kenneth F." <HashK@hdjdg.com>

Cc: "Jennifer Cline" <jcline@cityofmolalla.com>, "Cless Woodward" <cless@wtc-inc.com>, "Mat Warrington" <mat@wtc-inc.com>

Subject: Heintz Street - Submittal #7.1 - Precast Manholes Revised

Ken,

 

Please see the attached revised submittals for the precast manholes that includes the two elevation changes.

 

Thank you,

 

Nick Jones

Project Manager

Westech Construction, Inc.

Office: 503-777-7000

Cell: 503-969-1447

Fax: 503-774-3191