From: Jennifer Cline
Sent: Fri Apr 17 16:44:53 2015
To: Curtis Cooksey
Cc: hai@curran-mcleod.com; Dan Huff; Dennis Welle; Adam Shultz
Subject: RE: Heintz Street - Digouts & paving
Importance: Normal
Hi Curtis,
I spoke with Dick on the phone and the City will approve the change order work.
We agreed to
· edge grind 2” for the 6 feet and pave back 2” & 2” overlay
· grind 3” in the travel lanes pave back 3” & 2” overlay
· We will do a roll test to determine if dig-outs for stabilization are needed prior to paving
· There will be fabric for paving separation as you mentioned below
Regards,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Friday, April 17, 2015 4:18 PM
To: Jennifer Cline
Cc: hai@curran-mcleod.com
Subject: RE: Heintz Street - Digouts & paving
Hi Jennifer,
To grind Heintz st. @ 3” it will be $11,870.00
To pave Heintz 3” 514 ton+- @ $75.00 a ton $38,550.00
Total for Heintz $50,420.00
To grind Grange 3” @ 32’ wide it will be $18,055.00
To Pave Grange 3” 785 ton+- @ $75.00 a ton $58,875.00
Total for Grange $76,930.00
Total for both streets to grind and pave back the 3” $127,350.00
Deduct Item B-2 Pavement Repairs 2060 SY $21,939.00+
Deduct Item B-11 Geotextile Fabric 9000 SY $24,750.00
Let me know if you have any questions
Curtis
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Friday, April 17, 2015 10:57 AM
To: Hassan Ibrahim
Cc: Dan Huff; Curtis Cooksey
Subject: Heintz Street - Digouts & paving
Importance: High
Hi Hassan,
Dan and I went out to Heintz today looking at the planned dig-outs. The actual pavement failure well exceeds the planned dig-outs and extends from N Molalla to Grange. Our proposal is to do the following:
1. Prep trenches
2. Continue to grind 2” at curb line for 6 ft
3. Grind center roadway 3” for 28 ft
4. Place fabric for separation with in the 28 ft
5. Pave back 3” of PG 64-22, Level 3
6. Overlay 2” as planned
I believe this will save time and cost, and produced a better product for the City.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676