From: Jennifer Cline

Sent: Wed May 06 18:45:35 2015

To: Curtis Cooksey

Cc: hai@curran-mcleod.com; Dan Huff

Subject: RE: Heintz Street - Digouts & paving

Importance: Normal

Attachments: RE: Stowers Rd, Heintz St. and Grange Ave.;

 

Hi Curtis,

The project was not a complete 3” grind, there was a 2” – 6’ wide grind on the shoulders with and 3” grind on the remaining center of roadway.

Heintz St. – within the project limits shown on Sheets C10-C12,

· 2”- 6’ wide at edge of roadway

· 3” – Varies 24-25’ center of roadway

Grange Ave. – within the project limits shown on Sheets C8-C10,

· 2”- 6’ wide at edge of roadway

· 3” – Varies 30-31’wide center of roadway

I also verified the original S.Y. cost for Bid Item A-8. When you run the numbers it comes to $3.45/s.y. Can you please provide a justification as to why there is an increase of $0.85/s.y. between the two. Typically with an increase in quantities the unit price decreases.

I also ask that you take in account the City’s decision to change to grind saved several workings days. As calculated, the project must have reach substantial completion on 04/30. The request I received from you was on May 1, 2015. Even if additional days were to be granted for the previously planned added pavement repair I don’t see how the work could have been completed on time.

Please also show all bid items such as; A-8 and B-11 deleted and show a credit.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Tuesday, May 05, 2015 2:36 PM

To: 'Curtis Cooksey'

Cc: 'Jennifer Cline'

Subject: RE: Heintz Street - Digouts & paving

Hi Curtis,

Attached you will find Change Order #7 reflecting the grinding cost you provided below. Please sign and forward a copy to Jen for the City’s signature.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Friday, April 17, 2015 4:18 PM

To: Jennifer Cline

Cc: hai@curran-mcleod.com

Subject: RE: Heintz Street - Digouts & paving

Hi Jennifer,

To grind Heintz st. @ 3” it will be $11,870.00

To pave Heintz 3” 514 ton+- @ $75.00 a ton $38,550.00

Total for Heintz $50,420.00

To grind Grange 3” @ 32’ wide it will be $18,055.00

To Pave Grange 3” 785 ton+- @ $75.00 a ton $58,875.00

Total for Grange $76,930.00

Total for both streets to grind and pave back the 3” $127,350.00

Deduct Item B-2 Pavement Repairs 2060 SY $21,939.00+

Deduct Item B-11 Geotextile Fabric 9000 SY $24,750.00

Let me know if you have any questions

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, April 17, 2015 10:57 AM

To: Hassan Ibrahim

Cc: Dan Huff; Curtis Cooksey

Subject: Heintz Street - Digouts & paving

Importance: High

Hi Hassan,

Dan and I went out to Heintz today looking at the planned dig-outs. The actual pavement failure well exceeds the planned dig-outs and extends from N Molalla to Grange. Our proposal is to do the following:

1. Prep trenches

2. Continue to grind 2” at curb line for 6 ft

3. Grind center roadway 3” for 28 ft

4. Place fabric for separation with in the 28 ft

5. Pave back 3” of PG 64-22, Level 3

6. Overlay 2” as planned

I believe this will save time and cost, and produced a better product for the City.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676