From: Jennifer Cline
Sent: Thu May 07 09:16:31 2015
To: hai@curran-mcleod.com
Cc: Dan Huff
Subject: RE: Heintz Street - Digouts & paving
Importance: Normal
Hi Hassan,
The time to complete Bid item B.4 would have taken significantly longer to complete.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Thursday, May 07, 2015 6:04 AM
To: 'Jennifer Cline'
Cc: 'Dan Huff'
Subject: RE: Heintz Street - Digouts & paving
I don’t see what are you getting at in terms of contract time.
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Wednesday, May 06, 2015 6:57 PM
Cc: Dan Huff
Subject: RE: Heintz Street - Digouts & paving
Hi Hassan,
I’m ok on the cost of the MH adjustment, just want to wait and see if they give us a reduced unit cost based on added quantities and saved time to the contract for the change. I think I have a good point on the working days, since it is a critical path item.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Tuesday, May 05, 2015 2:36 PM
To: 'Curtis Cooksey'
Cc: 'Jennifer Cline'
Subject: RE: Heintz Street - Digouts & paving
Hi Curtis,
Attached you will find Change Order #7 reflecting the grinding cost you provided below. Please sign and forward a copy to Jen for the City’s signature.
Thanks,
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Friday, April 17, 2015 4:18 PM
To: Jennifer Cline
Subject: RE: Heintz Street - Digouts & paving
Hi Jennifer,
To grind Heintz st. @ 3” it will be $11,870.00
To pave Heintz 3” 514 ton+- @ $75.00 a ton $38,550.00
Total for Heintz $50,420.00
To grind Grange 3” @ 32’ wide it will be $18,055.00
To Pave Grange 3” 785 ton+- @ $75.00 a ton $58,875.00
Total for Grange $76,930.00
Total for both streets to grind and pave back the 3” $127,350.00
Deduct Item B-2 Pavement Repairs 2060 SY $21,939.00+
Deduct Item B-11 Geotextile Fabric 9000 SY $24,750.00
Let me know if you have any questions
Curtis
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Friday, April 17, 2015 10:57 AM
To: Hassan Ibrahim
Cc: Dan Huff; Curtis Cooksey
Subject: Heintz Street - Digouts & paving
Importance: High
Hi Hassan,
Dan and I went out to Heintz today looking at the planned dig-outs. The actual pavement failure well exceeds the planned dig-outs and extends from N Molalla to Grange. Our proposal is to do the following:
1. Prep trenches
2. Continue to grind 2” at curb line for 6 ft
3. Grind center roadway 3” for 28 ft
4. Place fabric for separation with in the 28 ft
5. Pave back 3” of PG 64-22, Level 3
6. Overlay 2” as planned
I believe this will save time and cost, and produced a better product for the City.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676