From: Jennifer Cline

Sent: Fri May 08 09:16:10 2015

To: hai@curran-mcleod.com

Cc: Dan Huff

Subject: RE: Heintz Street - Digouts & paving

Importance: Normal

 

I understand that, I’m asking Curtis to consider that if the City did not make the change to a grind EE would most like would have exceeded their working days and incurred Liquidated Damages.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Friday, May 08, 2015 5:53 AM

To: 'Jennifer Cline'

Cc: 'Dan Huff'

Subject: RE: Heintz Street - Digouts & paving

The contract doesn’t provide any incentives or compensations for completing the work sooner.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Thursday, May 07, 2015 9:15 AM

To: hai@curran-mcleod.com

Cc: Dan Huff

Subject: RE: Heintz Street - Digouts & paving

Hi Hassan,

The time to complete Bid item B.4 would have taken significantly longer to complete.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Thursday, May 07, 2015 6:04 AM

To: 'Jennifer Cline'

Cc: 'Dan Huff'

Subject: RE: Heintz Street - Digouts & paving

I don’t see what are you getting at in terms of contract time.

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, May 06, 2015 6:57 PM

To: hai@curran-mcleod.com

Cc: Dan Huff

Subject: RE: Heintz Street - Digouts & paving

Hi Hassan,

I’m ok on the cost of the MH adjustment, just want to wait and see if they give us a reduced unit cost based on added quantities and saved time to the contract for the change. I think I have a good point on the working days, since it is a critical path item.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Tuesday, May 05, 2015 2:36 PM

To: 'Curtis Cooksey'

Cc: 'Jennifer Cline'

Subject: RE: Heintz Street - Digouts & paving

Hi Curtis,

Attached you will find Change Order #7 reflecting the grinding cost you provided below. Please sign and forward a copy to Jen for the City’s signature.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Friday, April 17, 2015 4:18 PM

To: Jennifer Cline

Cc: hai@curran-mcleod.com

Subject: RE: Heintz Street - Digouts & paving

Hi Jennifer,

To grind Heintz st. @ 3” it will be $11,870.00

To pave Heintz 3” 514 ton+- @ $75.00 a ton $38,550.00

Total for Heintz $50,420.00

To grind Grange 3” @ 32’ wide it will be $18,055.00

To Pave Grange 3” 785 ton+- @ $75.00 a ton $58,875.00

Total for Grange $76,930.00

Total for both streets to grind and pave back the 3” $127,350.00

Deduct Item B-2 Pavement Repairs 2060 SY $21,939.00+

Deduct Item B-11 Geotextile Fabric 9000 SY $24,750.00

Let me know if you have any questions

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, April 17, 2015 10:57 AM

To: Hassan Ibrahim

Cc: Dan Huff; Curtis Cooksey

Subject: Heintz Street - Digouts & paving

Importance: High

Hi Hassan,

Dan and I went out to Heintz today looking at the planned dig-outs. The actual pavement failure well exceeds the planned dig-outs and extends from N Molalla to Grange. Our proposal is to do the following:

1. Prep trenches

2. Continue to grind 2” at curb line for 6 ft

3. Grind center roadway 3” for 28 ft

4. Place fabric for separation with in the 28 ft

5. Pave back 3” of PG 64-22, Level 3

6. Overlay 2” as planned

I believe this will save time and cost, and produced a better product for the City.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C: