From: Jennifer Cline

Sent: Thu Jun 18 11:02:18 2015

To: Sharar, Darlene K.

Cc: Hash, Kenneth F.; Dan Huff

Subject: Re: Heintz St. - PGE #M1594768

Importance: Normal

Attachments: image001.gif;

 

Do I need to put a call into PGE to speed this up? I can start by contacting Andrew on my end

 

Jenn

 

Sent from my iPhone

 

On Jun 18, 2015, at 9:43 AM, Luanne Berkey <Luanne.Berkey@pgn.com> wrote:

 

image

It can be several weeks.

Thanks,

Luanne

From: Sharar, Darlene K. [mailto:ShararD@hdjdg.com]

Sent: Wednesday, June 17, 2015 10:08 AM

To: Luanne Berkey

Cc: Hash, Kenneth F.; 'Jennifer Cline'

Subject: RE: Heintz St. - PGE #M1594768

Hello Luanne -

The project will begin the first week of July.

For the payment, I am including the City Public Works Director and project manager.

When you note that the material and poles can take several weeks – what is the delivery timeframe that PGE has been experiencing recently?

Thank you.

Darlene K. Sharar | Construction Management

HDJ DESIGN GROUP, PLLC

Engineers | Landscape Architects | Planners | Surveyors

314 W. 15th Street, Vancouver, WA 98660

Phone: 360/695-3488 Fax: 360/695-8767

ShararD@hdjdg.com

From: Luanne Berkey [mailto:Luanne.Berkey@pgn.com]

Sent: Wednesday, June 17, 2015 7:21 AM

To: Sharar, Darlene K.

Subject: Heintz St. - PGE #M1594768

Good morning –

Do you have a time frame when this project will go? We will need payment before ordering the material and poles can take several weeks for delivery.

Thanks,

Luanne Berkey | Lighting Specialist

Service & Design

Portland General Electric

4245 Kale St. NE | Salem, Oregon 97305

| (: (503) 463-6161 7: (503) 463-4308 | *: luanne.berkey@pgn.com

<image002.jpg>