From: Jennifer Cline

Sent: Tue Sep 08 14:49:39 2015

To: Hash, Kenneth F.

Subject: RE: Heintz - Submittal #8 - Manhole base and Manhole Channel Concrete Mix Design

Importance: Normal

 

Thanks Ken

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Hash, Kenneth F. [mailto:HashK@hdjdg.com]

Sent: Tuesday, September 08, 2015 2:03 PM

To: Jenn Cline (jcline@cityofmolalla.com) <jcline@cityofmolalla.com>

Subject: FW: Heintz - Submittal #8 - Manhole base and Manhole Channel Concrete Mix Design

Yes – channels and bases are class 3000.

This mix design is approvable.

Ken

From: Nick Jones [mailto:nickj@wtc-inc.com]

Sent: Tuesday, September 08, 2015 12:08 PM

To: Hash, Kenneth F. <HashK@hdjdg.com>

Cc: Jennifer Cline <jcline@cityofmolalla.com>

Subject: Heintz - Submittal #8 - Manhole base and Manhole Channel Concrete Mix Design

Ken,

Just checking my records, have I submitted the concrete mix design for the manhole bases and channels? This is MRM’s standard 3,000 psi mix design. We are schedules to pour on Thursday this week.

Thank you,

Nick Jones

Project Manager

Westech Construction, Inc.

Office: 503-777-7000

Cell: 503-969-1447

Fax: 503-774-3191