From: Jennifer Cline
Sent: Tue Sep 08 14:49:39 2015
To: Hash, Kenneth F.
Subject: RE: Heintz - Submittal #8 - Manhole base and Manhole Channel Concrete Mix Design
Importance: Normal
Thanks Ken
Jennifer Cline, P.E. | Public Works Director
Licensed in OR, WA
117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038
O: 503.759.0218 | F: 503.829.3676
From: Hash, Kenneth F. [mailto:HashK@hdjdg.com]
Sent: Tuesday, September 08, 2015 2:03 PM
To: Jenn Cline (jcline@cityofmolalla.com) <jcline@cityofmolalla.com>
Subject: FW: Heintz - Submittal #8 - Manhole base and Manhole Channel Concrete Mix Design
Yes – channels and bases are class 3000.
This mix design is approvable.
Ken
From: Nick Jones [mailto:nickj@wtc-inc.com]
Sent: Tuesday, September 08, 2015 12:08 PM
To: Hash, Kenneth F. <HashK@hdjdg.com>
Cc: Jennifer Cline <jcline@cityofmolalla.com>
Subject: Heintz - Submittal #8 - Manhole base and Manhole Channel Concrete Mix Design
Ken,
Just checking my records, have I submitted the concrete mix design for the manhole bases and channels? This is MRM’s standard 3,000 psi mix design. We are schedules to pour on Thursday this week.
Thank you,
Nick Jones
Project Manager
Westech Construction, Inc.
Office: 503-777-7000
Cell: 503-969-1447
Fax: 503-774-3191