From: Hassan Ibrahim
Sent: Tue Feb 17 10:18:13 2015
To: 'Curtis Cooksey'
Cc: jcline@cityofmolalla.com
Subject: RE: Cost to raise catchbasin
Importance: Normal
You will be welding a riser to the catch basin frame at the most northerly driveway to the Church property on Grange. The cost sounds reasonable, let’s wait for Jenn’s response before we move ahead.
Thanks Curtis,
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Tuesday, February 17, 2015 10:08 AM
To: hai@curran-mcleod.com
Cc: jcline@cityofmolalla.com
Subject: Cost to raise catchbasin
Hi Hassan,
Mike said you wanted a price to raise a CB frame 3”.
It will cost $275.00 to raise the existing grate 3”.
Curtis