From: Hassan Ibrahim
Sent: Fri Apr 17 08:12:36 2015
To: 'Jennifer Cline'
Subject: RE: Additional C.O requests
Importance: Normal
I talked to Bo and we have a new catch basin in this corner, please send me
a sketch to clarify what you need to be done?
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
-----Original Message-----
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Friday, April 17, 2015 8:00 AM
To: Hassan Ibrahim
Subject: Re: Additional C.O requests
I don't think the storm drain repair was 10". Please verify w Bob.
Sent from my iPhone
> On Apr 17, 2015, at 6:33 AM, Hassan Ibrahim <hai@curran-mcleod.com> wrote:
>
> Hi Curtis,
>
>
>
> As per the City's request attached please find the location of the
> proposed changes, also see below our responses in red.
>
>
>
> Should you have any questions, please let me know.
>
>
>
> Thanks,
>
> --------------------
> Hassan Ibrahim, P.E.
> CURRAN-McLEOD, INC.
> 6655 SW Hampton St, Ste. 210
> Portland, OR 97223
> Tel: 503-684-3478
> Fax: 503-624-8247
> Cell: 503-807-2737
> email: hai@curran-mcleod.com
>
>
>
> From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
> Sent: Thursday, April 16, 2015 2:59 PM
> To: Hassan Ibrahim
> Cc: 'Curtis Cooksey'; Dan Huff; Heather Penni; Dennis Welle; 'Adam Shultz'
> Subject: Additional C.O requests
>
>
>
> Hi Hassan,
>
>
>
> The City would like to request a change order for the 3 additional items.
>
>
>
> . Storm drain pipe repair from the catch basin located at the NE
> corner of 6th St and Stowers Ave. This can be paid under 10" DI Pipe
> as per
> CO#5 @$47.10/ LF. However, it can be included as a line item in a new CO
#7.
>
> . Construct a new storm Type G-2 Basin at the NW corner of 7th and
> Stowers and connecting it to the storm main in 7th St. There is
> nowhere for the water flowing to the south to drain. The next nearest
> storm basin is on 7th and Cole at least 100 yards away with almost 0%
slope in some areas.
> This can be paid under 10" DI Pipe as per CO#5 @$47.10/ LF. However,
> it can be included as a line item in a new CO #7.
>
> . Add a water valve at Heintz and Kennel for the south main on
> Kennel. There currently is no ability to shut off the water south on
> Kennel without turning off other users water as well. 1 existing
> valve is to be abandoned as well. Need a price for this one.
>
> . Add 1 day to the schedule for determining the driveway conflicts
> on Stowers. I am thinking 2 days (one for the storm work and one for
> the valve installation)
>
>
>
> Jennifer Cline, P.E.
>
> City of Molalla
>
> Public Works Director
>
> O: 503.759.0218
>
> F: 503.829.3676
>
>
> <file:///C:\Users\jsherman\AppData\Roaming\Microsoft\Signatures\jennif
> er%20c
> line_files\Image001.jpg>
>
> <Stowers Changes.pdf>