From: Jennifer Cline
Sent: Fri Apr 17 10:57:17 2015
To: Hassan Ibrahim
Cc: Dan Huff; 'Curtis Cooksey'
Subject: Heintz Street - Digouts & paving
Importance: High
Hi Hassan,
Dan and I went out to Heintz today looking at the planned dig-outs. The actual pavement failure well exceeds the planned dig-outs and extends from N Molalla to Grange. Our proposal is to do the following:
1. Prep trenches
2. Continue to grind 2” at curb line for 6 ft
3. Grind center roadway 3” for 28 ft
4. Place fabric for separation with in the 28 ft
5. Pave back 3” of PG 64-22, Level 3
6. Overlay 2” as planned
I believe this will save time and cost, and produced a better product for the City.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676