From: Hassan Ibrahim
Sent: Wed Jan 21 06:36:48 2015
To: 'Curtis Cooksey'
Cc: 'Jennifer Cline'
Subject: FW: Stowers Rd. Grange Ave. & Heintz St.
Importance: Normal
Hi Curtis,
The TC at the intersection of Granage and the Hwy 211 is accepted by ODOT. Please see below. 7 day notification to Justin is needed.
Thanks.
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: SHOEMAKER Justin D [mailto:Justin.D.SHOEMAKER@odot.state.or.us]
Sent: Tuesday, January 20, 2015 9:30 AM
To: hai@curran-mcleod.com
Subject: RE: Stowers Rd. Grange Ave. & Heintz St.
Nope
Justin Shoemaker
Project Development Liaison
Region 1 Project Services
123 NW Flanders Street
Portland, OR 97209
(503)731-8486
Email: justin.d.shoemaker@odot.state.or.us
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Monday, January 19, 2015 6:56 AM
To: SHOEMAKER Justin D
Cc: jcline@cityofmolalla.com; 'Curtis Cooksey'
Subject: FW: Stowers Rd. Grange Ave. & Heintz St.
Hi Justin,
Do you still have any concerns with the TC other than 7 day inspection notification prior to the start of the work?
Thanks,
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Friday, January 16, 2015 3:05 PM
Subject: Stowers Rd. Grange Ave. & Heintz St.
Hi Hassan,
I’ve revised the traffic control plan, ODOT wanted me to have the pedestrians cross HWY 211, before they get to the construction zone when we do the sidewalk ramps.
Thanks
Curtis