From: Hassan Ibrahim

Sent: Tue May 05 14:46:14 2015

To: 'Jennifer Cline'

Subject: FW: Over-ex/Dig-outs Measurements

Importance: Normal

Attachments: Eagle_Elsner006.PDF; Eagle_Elsner007.PDF;

 

Hi Jen,

EE are showing 811.4 CY of over excavation @ $88.00/CY totaling $71,403.20?

What are your thoughts?

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Tuesday, May 05, 2015 10:42 AM

To: Jennifer Cline

Cc: hai@curran-mcleod.com

Subject: RE: Over-ex/Dig-outs Measurements

Hi Jennifer,

I’m sending you the locations and areas of the subgrade stabilization.

Let me know if you have any questions.

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Tuesday, April 28, 2015 9:23 AM

To: Curtis Cooksey

Cc: Hassan Ibrahim; Dan Huff

Subject: Over-ex/Dig-outs Measurements

Hi Curtis,

We have had several dig-outs on this project for subgrade stabilization as you are aware. I would like to verify Barbs notes/spreadsheet to confirm measurement areas for payment. I’m assuming the measurements were also done for the few dig-outs on Grange and Heintz as well by Walter?

Thank you,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C: