From: Jennifer Cline
Sent: Thu Jan 22 10:36:54 2015
To: Hassan Ibrahim; Garrett Edmunds; Dan Zinder
Cc: Dan Huff; Heather Penni
Subject: Water Main on Stowers
Importance: Normal
Hi,
I talked to Garrett regarding the water main that exists on Stowers, it currently is AC. If possible we would like to have the main replaced and abandoned in the ground. I did not realize that it was AC and missed that it was not included in project.
A few points to discuss between all of us timely..
· Was the water main on the previous Stowers project upgraded and if so to what type and size?
· Will this be an upgrade for the second section of Stowers? And if so do we have time to get approval for the upgrade through Oregon DHS?
· What is the cost? And can this be paid under the current SDC methodology?
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676