Hi Hassan,

I spoke with Dennis our Public Works lead and he has recommended extending the water main approximately an additional 15-ft west on 7th St from Stowers intersection. The current tie in is located right at the existing forced sewer main. He would has recommenced extending the line under the forced sewer main and connecting on the west side. This would remove the need from having to safely locate and excavate around the forced main in the future. Can you pass the minor change on to the Eagle-Elsner.

I am unsure if there will be a need for 45-deg bend or fittings to maintain proper separation from the force main at this time. This should be looked at.