Hi Gerald,

Here’s a link of everything I have received from Multitech in the last week. I have not had time to go through any of this yet.

https://www.dropbox.com/sh/g7z20swoexvgmp6/AACP6a3QdqZf4LyX9NUBsKOga?dl=0

It also looks like Mark Grenz sent the updated Stormwater calc sheets. I see they have made the corrections you requested with the exception that you still can’t tell how they calculated the Allow Qa in the Design Data in Table 1b for each orifice. It appears to be a percentage of the final outflow (0.82 cfs) based on the “Percent of Outflow” for each Orifice in the Site Poroportioanl Assignments Table.

Thanks,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676