From: Jennifer Cline
Sent: Thu May 28 12:45:36 2015
To: Mark Strandberg; Phillip Bender
Cc: 'J.W. Ring'; 'Christine Hein'; Dan Huff
Subject: SCADA Instrument & Control Plans
Importance: Normal
Attachments: 2006_WastewaterTreatmentPlantImprovsPlans_Reduced.pdf; Hi, Attached are the plans for the last upgrade with include in Section I details of the Instrument & Control Plans for the SCADA system. This is the layout of the system which includes a block diagram. I/S completed the work yesterday at the plant. I have not received a new block diagram for the changes, but will ask when we might receive it. Jennifer Cline, P.E. Public Works Director 117 N Molalla Ave. PO Box 248 * Molalla, OR 97038 O: 503.759.0218 F: 503.829.3676