From: Jennifer Cline

Sent: Fri Aug 21 11:49:01 2015

To: Lee, Rob

Cc: Dan Zinder

Subject: RFP for CCTV question

Importance: Normal

Attachments: DEQ_Map_v3.pdf;

 

Hi Rob,

Assuming the following:

· CCTV inspection is approximately $1.25 incl. mob & traffic control support,

· the work to be completed totals less than $100,000.00,

· estimating between 70,000-75,000 LF of sewer line to be inspected.

What basins do you recommend to prioritize for the contractor to complete this fiscal year?

Thank you and have a great weekend.

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

image