From: Jennifer Cline

Sent: Tue Mar 29 19:31:46 2016

To: Gerald Fisher

Subject: Re: WWTP DEQ submittals

Importance: Normal

 

I'm off Friday, so Monday is good too

 

Sent from my iPhone

 

On Mar 29, 2016, at 6:08 PM, Gerald Fisher <geraldf@pdgnw.com> wrote:

 

Possibly Friday discussion.

 

Gerald Fisher, PE, Senior Project Manager

Project Delivery Group

3150 22nd Street SE

Salem, OR 97302

503.364.4004 (office)

503.679.9237 (cell)

 

Sent from my 4G LTE Smartphone

 

 

-------- Original message --------

From: Jennifer Cline <jcline@cityofmolalla.com>

Date: 03/29/2016 5:56 PM (GMT-08:00)

To: Gerald Fisher <geraldf@pdgnw.com>

Subject: WWTP DEQ submittals

 

Hi Gerald,

I have two possible small scale project requests for either you or a combination of you and Dyers expertise for the WWTP. The possible small project requests are as follows:

· Review the updated O & M Manual. I don’t believe this needs to be stamped by an Engineer, but we could have it submitted by yourself or Dyer to DEQ on behalf of the City. I don’t know DEQ’s requirements on O&M Manual updates at this point.

· Help develop a plan and specifications submittal to DEQ for the diffuser aeration system we purchased to install at Lagoon #1. I do not have the ability to draft a plan sheet. Most of the specifications are going to be as manufacturers recommendations.

Let’s discuss to see if we need to assistance with submitting these items to DEQ.

Thanks,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

image