From: Jennifer Cline

Sent: Mon Jul 20 15:53:33 2015

To: Hash, Kenneth F.

Subject: RE: Westech pipe submittal

Importance: Normal

 

Ok,

 

I also wanted to check to see if you or your staff will be completing pay notes for the work complete? I know we discussed this before, but just wanted to verify that. Nate was talking today about going over pay items weekly to verify completed quantities.

 

Jennifer Cline, P.E.

 

City of Molalla

 

Public Works Director

 

O: 503.759.0218

 

F: 503.829.3676

 

 

 

-----Original Message-----

From: Hash, Kenneth F. [mailto:HashK@hdjdg.com]

Sent: Monday, July 20, 2015 3:44 PM

To: Jenn Cline

Cc: Buehler, John A.

Subject: Westech pipe submittal

 

Jenn

Westech wants to start working on the west end waterline Tuesday. We have reviewed their pipe submittal and have returned it to Nick for added information. John or I will send it to you shortly.

Much of the submittal can be approved as is, parts need added info.

The pipe for Tuesday's work is ok to approved.

 

Sent from my iPhone

 

 

DISCLAIMER: This electronic message and any attachments are supplied in good faith and are believed to be virus free. HDJ Design Group, PLLC accepts no responsibility for the damage or loss (arising from negligence or otherwise) which may occur through the use or transmission of this message and attachments.

 

The contents of this electronic message and any attachments are intended only for the addressee and may contain privileged or confidential information. If you are not the addressee, you are notified that any transmission, distribution, downloading, printing or photocopying of the contents of this message or attachments is strictly prohibited. The privilege of confidentiality attached to this message and any attachments is not waived, lost or destroyed by reason of mistaken delivery to you. If you receive this message in error, please notify the sender by return email or telephone by calling (360) 695-3488.