From: Jennifer Cline
Sent: Thu Sep 04 15:14:13 2014
To: cjm@curran-mcleod.com
Cc: hai@curran-mcleod.com; Garrett Edmunds; Keith Stiglbauer
Subject: RE: Water Treatment Plant & Vac Truck Dump Site Designs
Importance: Normal
Thank you, I will check back in with you in a few weeks if I don’t hear from you first.
Jenn
From: Curt McLeod [mailto:cjm@curran-mcleod.com]
Sent: Thursday, September 04, 2014 1:07 PM
To: 'Jennifer Cline'
Cc: Hassan Ibrahim
Subject: RE: Water Treatment Plant & Vac Truck Dump Site Designs
Hi Jen,
I will work to complete the plans as soon as possible and determine how best to proceed securing a contractor. I have been tied up on several fronts and apologize for the delays. I will work to make it up to you. Give me two weeks and I will get back with the WWTP project.
The WTP project should be to duplicate what Keith already installed on the westerly pond. The vertical column with orifices should work great to detain the backwash and minimize discharge rates. I need to get information on drainage law and will then coordinate with Keith.
************************************
Curt McLeod P.E.
CURRAN-McLEOD, INC.
6655 S.W. Hampton Street, Suite 210
Portland, Oregon 97223
T: (503) 684-3478
F: (503) 624-8247
C: (503) 475-0431
email: cjm@curran-mcleod.com
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Thursday, September 04, 2014 11:44 AM
Cc: 'Keith Stiglbauer'; Garrett Edmunds; Dan Huff; hai@curran-mcleod.com
Subject: Water Treatment Plant & Vac Truck Dump Site Designs
Hi Curt,
Following up with on the designs of the flow restrictor at the backwash pond at the Water Treatment Facility and Vac Truck Dump Site at the Waste Water Treatment Facility.
We are getting ready to start using the Vac truck to clean out our sanitary sewer lines before winter. I need to know if we have time to select a contractor and construct the station before the inclement weather begins.
Regards,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.829.6855 Ext. #218
F: 503.829.3676