From: Jennifer Cline

Sent: Tue Jun 30 13:45:31 2015

To: Munro, Gordon

Cc: Ryan h

Subject: RE: water transmission line

Importance: Normal

Attachments: image002.png;

 

Hi Gordon,

Yes, that is still the plan. Along with identifying a water well source location for the city to increase capacity. The City may decide to go out with a RFP for engineering for these projects. I should be available in the morning.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: Munro, Gordon [mailto:Gordon.Munro@tetratech.com]

Sent: Tuesday, June 30, 2015 1:12 PM

To: Jennifer Cline

Subject: water transmission line

Hi Jennifer

Last December we chatted about a potential water transmission pipe from the WTP to the community. I thought I would check in with you to see if the City is planning to do that project and what the schedule might be. Also, I will be in the area Wednesday mid morning and thought I might drop by to say hello.

Thanks

Gordon

PS – Hope the dealings with the DEQ are going well.

Gordon Munro, (PE) | Senior Civil Project Manager

Direct: 503 598-2530 | Cell: 971 330-5168 | Main: 503.684.9097 | Fax: 503.598.0583

gordon.munro@tetratech.com

 

Tetra Tech

Complex World, Clear Solutions

15350 SW Sequoia Parkway, Suite 220 | Portland, OR 97224 | www.tetratech.com

 

PLEASE NOTE: This message, including any attachments, may include privileged, confidential and/or inside information. Any distribution or use of this communication by anyone other than the intended recipient is strictly prohibited and may be unlawful. If you are not the intended recipient, please notify the sender by replying to this message and then delete it from your system.