From: Jennifer Cline
Sent: Tue Oct 28 08:43:31 2014
To: Garrett Edmunds
Subject: RE: Water Line Work Descriptions
Importance: Normal
Thank You,
Have a safe trip and let me know if you have any issues registering.
Jenn
From: Garrett Edmunds [mailto:gedmunds@cityofmolalla.com]
Sent: Tuesday, October 28, 2014 8:39 AM
To: Jennifer Cline
Subject: RE: Water Line Work Descriptions
Jennifer,
Metzler Water Line
· Begin replacement at Metzler Ave. and West Main Street to Metzler and 7th.
· Existing water line is 6 inch, consisting of steal, AC, and plastic water lines.
· Replace with 8 inch plastic.
3rd Water line
· Begin replacement at Lola Ave. and 3rd to Berkley and 3rd.
· Existing water line is 4 inch steal.
· Replace with 6 inch plastic.
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Thursday, October 23, 2014 8:21 AM
To: Garrett Edmunds
Subject: Water Line Work Descriptions
Hi Garrett,
Will you please write me a description of the work to complete the water line repairs on Metzler and 5th.
Please include:
The beginning and end project limits
Existing water line size
Proposed water line size
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676