From: Jennifer Cline

Sent: Wed Apr 27 14:50:28 2016

To: engineers@molalla.com

Cc: Sarah Kennedy; Mike Houck; Adam Shultz; Greg Spence; Chris Link

Subject: RE: Utility conflict

Importance: Normal

 

Hi Gary,

The below indicated conflict is in regards to a MCC fiber line that currently crosses N Molalla on the south side of the Robbins intersection. The line will need to be adjusted above or below the proposed 30” storm line to continue the construction.

Please contact Greg Spence with M.L. Houck construction for more information. (503) 931-3982. If you have other questions feel free to give me a call at 503-759-0218 (direct).

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Greg Spence [mailto:greg@houckco.com]

Sent: Wednesday, April 27, 2016 11:26 AM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>; 'Chris Link' <Chris.Link@msa-ep.com>

Cc: 'Sarah Kennedy' <sarah@houckco.com>; 'Mike Houck' <mike@houckco.com>

Subject: Utility conflict

Jennifer,

At Sta. 24+63 +-, communication conduits in conflict with 30 “ storm line.

Top of conduits 362.12, design flow line 30” storm 360.40+-.

Contractor is not installing storm between SDMH # 16, and SDMN 14, to allow for relocate of utility.

Call if you need more information.

Thank you

Greg Spence

503-931-3982