From: Jennifer Cline
Sent: Wed Apr 27 14:50:28 2016
To: engineers@molalla.com
Cc: Sarah Kennedy; Mike Houck; Adam Shultz; Greg Spence; Chris Link
Subject: RE: Utility conflict
Importance: Normal
Hi Gary,
The below indicated conflict is in regards to a MCC fiber line that currently crosses N Molalla on the south side of the Robbins intersection. The line will need to be adjusted above or below the proposed 30” storm line to continue the construction.
Please contact Greg Spence with M.L. Houck construction for more information. (503) 931-3982. If you have other questions feel free to give me a call at 503-759-0218 (direct).
Jennifer Cline, P.E. | Public Works Director
Licensed in OR, WA
117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038
O: 503.759.0218 | F: 503.829.3676
From: Greg Spence [mailto:greg@houckco.com]
Sent: Wednesday, April 27, 2016 11:26 AM
To: 'Jennifer Cline' <jcline@cityofmolalla.com>; 'Chris Link' <Chris.Link@msa-ep.com>
Cc: 'Sarah Kennedy' <sarah@houckco.com>; 'Mike Houck' <mike@houckco.com>
Subject: Utility conflict
Jennifer,
At Sta. 24+63 +-, communication conduits in conflict with 30 “ storm line.
Top of conduits 362.12, design flow line 30” storm 360.40+-.
Contractor is not installing storm between SDMH # 16, and SDMN 14, to allow for relocate of utility.
Call if you need more information.
Thank you
Greg Spence
503-931-3982