From: Jennifer Cline

Sent: Wed Apr 27 14:53:53 2016

To: Greg Spence

Cc: Sarah Kennedy; Mike Houck; Daphne Lisac; Chris Link

Subject: RE: Utility Conflict ( water)

Importance: Normal

 

Hi Greg,

Do you have a proposed adjustment to the staging or water line design to address the conflict?

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Greg Spence [mailto:greg@houckco.com]

Sent: Wednesday, April 27, 2016 1:54 PM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>; 'Chris Link' <Chris.Link@msa-ep.com>

Cc: 'Sarah Kennedy' <sarah@houckco.com>; 'Mike Houck' <mike@houckco.com>

Subject: Utility Conflict ( water)

Jennifer,

Existing water main Sta. 24+88 +-, in conflict with 30” storm line.

Top of water main 362.7, design flow line 360.3 +-, Please advise. This conflict is also between SDMH 16, and SDMH 14.

Water main to be replaced in stage 2 of project.

All if you need more Information,

Thank you

Greg Spence

503-931-3982