From: Jennifer Cline

Sent: Tue Mar 24 08:57:23 2015

To: Hash, Kenneth F.

Cc: Heather Penni; Dan Huff

Subject: RE: Updated Estimates

Importance: Normal

Attachments: 2015-03-23_Budget.xls;

 

Hi Ken,

Looks good to me for now. I will go this over with Heather next week when she returns from vacation. Will you use the same form when you update for 30% construction on Heintz?

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Hash, Kenneth F. [mailto:HashK@hdjdg.com]

Sent: Monday, March 23, 2015 3:56 PM

To: Jennifer Cline

Subject: RE: Updated Estimates

Will something like this work?

The only updated costs are on the PE phase of Heintz Street.

We will have a 30% estimate next week and I can fill in that number then.

I plan to highlight changes in yellow.

I have aged costs by quarter. Will this work?

My assumptions are:

· That design work on Molalla Ave is completed by the first of the year.

· Molalla Ave is completely constructed next year.

· The remainder of design is completed over next winter/spring for a 2017 construction season.

By the way

MSA will be doing the heavy lifting on Molalla Ave with HDJ support. I just received their scope and budget and will have design numbers soon.

HDJ will complete the remainder of the design work.

Ken

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Tuesday, March 17, 2015 6:08 PM

To: Hash, Kenneth F.

Subject: Updated Estimates

Hi Ken,

Do you know when you may have an updated preliminary estimate? If you have the ability to age the estimate over the next 3 years. That would be helpful for budgeting.

Good to see you today J

Thanks

Jenn