From: Jennifer Cline

Sent: Mon Apr 25 13:52:02 2016

To: Luanne Berkey

Subject: Re: Street Light Project Packet - City of Molalla - Molalla Ave. Improvement Project - PGE #M1678824

Importance: Normal

 

No, this work will be done under a City contract as a urban renewal improvement project.

 

Thanks,

JC

 

Sent from my iPhone

 

On Apr 25, 2016, at 1:35 PM, Luanne Berkey <Luanne.Berkey@pgn.com> wrote:

 

<image001.gif>

Does PGE need a City of Molalla right-of-way permit on this project? I assume the contractor is pulling a permit for their work, wasn’t sure if we needed one also to occupy the conduit.

Thanks,

Luanne

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Monday, April 18, 2016 1:12 PM

To: Luanne Berkey; Chris Link

Cc: sharard@hdjdg.com; Jonathan Gellings; Greg Spence

Subject: RE: Street Light Project Packet - City of Molalla - Molalla Ave. Improvement Project - PGE #M1678824

Hi Luanne,

Does this change the agreement at all?

Regards.

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Luanne Berkey [mailto:Luanne.Berkey@pgn.com]

Sent: Monday, April 18, 2016 1:10 PM

To: Chris Link <Chris.Link@msa-ep.com>

Cc: Jennifer Cline <jcline@cityofmolalla.com>; sharard@hdjdg.com; Jonathan Gellings <Jonathan.Gellings@msa-ep.com>; Greg Spence (greg@houckco.com) <greg@houckco.com>

Subject: RE: Street Light Project Packet - City of Molalla - Molalla Ave. Improvement Project - PGE #M1678824

Hi Chris –

See attached construction drawing with changes noted. Let me know if there are any questions.

Thanks,

Luanne

Luanne Berkey | Lighting Specialist

Service & Design

Portland General Electric

4245 Kale St. NE | Salem, Oregon 97305

| (: (503) 463-6161 7: (503) 463-4308 | *: luanne.berkey@pgn.com

<image002.jpg>

From: Chris Link [mailto:Chris.Link@msa-ep.com]

Sent: Thursday, April 14, 2016 2:30 PM

To: Luanne Berkey

Cc: Jennifer Cline; sharard@hdjdg.com; Jonathan Gellings

Subject: RE: Street Light Project Packet - City of Molalla - Molalla Ave. Improvement Project - PGE #M1678824

Hi Luanne,

It appears that there are a few discrepancies between PGE’s plan and our design that could affect the contractor’s means and methods for conduit installation.

PGE’s plan shows conduit being installed in the area in front of City Hall where the existing sidewalk is to remain. The conduit would need to be directionally bored or jack and bored. Also, it appears that you plan is not showing a conduit crossing on the east side of Ross St. This will affect their power distribution plan.

See attached PDF noting the discrepancies. Can you take a look and let me know if you can revise things accordingly?

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

From: Luanne Berkey [mailto:Luanne.Berkey@pgn.com]

Sent: Thursday, April 14, 2016 8:22 AM

To: Greg Spence (greg@houckco.com) <greg@houckco.com>; Chris Link <Chris.Link@msa-ep.com>

Cc: Jennifer Cline <jcline@cityofmolalla.com>

Subject: Street Light Project Packet - City of Molalla - Molalla Ave. Improvement Project - PGE #M1678824

Good morning –

Attached you will find our customer responsibility letter for street lighting, a PGE construction drawing of the project, Approved Material List and our standard for the anchor base pole installation.

The anchor base for the streetlight poles and ground rods need to be installed at the same time the conduit system is installed. PGE will provide these and your contractor may call Old Castle @ 503.682.2844 to schedule the drop ship to your staging location (reference WR#M1678824).They will need to pick up the ground rods from our Woodburn storeroom located at 2079 Progress Way, Woodburn, phone # 503.980.2137.

Please pass this information on to any contractors who may be doing any portion of this work. A pre-construction meeting is required on site, and all conduit work must be inspected before you backfill. Please call PGE @ (503) 323-6700 to schedule inspections.

Please feel free to call me if you have any questions or concerns.

Luanne Berkey | Lighting Specialist

Service & Design

Portland General Electric

4245 Kale St. NE | Salem, Oregon 97305

| (: (503) 463-6161 7: (503) 463-4308 | *: luanne.berkey@pgn.com

<image004.jpg>