Attached are the invoices for the overlay at Stowers and 8th.
The manhole at the entrance into the project on the East side of Stowers and South side of 8th is a phone vault and is not a normal manhole riser. With that being said you will need to get ahold of them and have them adjust it to grade and patch around it.
Please provide a copy of the invoices for Smelser and Flores to them.