From: Jennifer Cline
Sent: Fri Mar 06 08:16:19 2015
To: Carlo Zeppetella
Cc: Nicolas Lennartz
Subject: RE: Stowers Construction & Driveway
Importance: Normal
Hi Carlo,
Here is the estimation of the cost for your approach.
Assumptions: 24 ft approach x 5 ft wide.
4” Concrete Sidewalk or Driveway incl. excavation and 2” leveling rock: $45/sq. yd.
24’ x 5’ = 120 s.f./9 s.f./s.y. = 13.33 s.y. x $45/s.y. = ~$600.00
50% of $600 = $300.00 shared cost of the approach.
Please let the City know how you would like to proceed?
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Carlo Zeppetella [mailto:carlo@siteworksportland.com]
Sent: Tuesday, March 03, 2015 4:56 PM
To: Jennifer Cline
Cc: Jamie
Subject: Re: Stowers Construction & Driveway
I would like to get exact cost for my budget , as you know an approximate cost can double very quickly as unforeseen's always seen to happen . It will be very nice to have a wider driveway , we have been driving over the curb way too long .
Thanks Carlo Zeppetella
General superintendent
Siteworks Design/Build
Sent from my iPhone
On Mar 3, 2015, at 4:43 PM, Jennifer Cline <jcline@cityofmolalla.com> wrote:
Hi Carlo,
I’m am writing in response to your questions presented to Nicholas.
(1) The contractor has a general schedule of the work on Stowers. However, the schedule is not detailed in the daily location of work. The contractor has begun excavating the watermain on Stowers this week working from the north to south end. Up to this point the utility companies have been on site making adjustments. The waterline work will continue until complete, followed by water service connections, pavement removal, sidewalk and curb and then paving. I would expect intermittent delays throughout the project for up to 20 minutes at a time. You may speak to the contractor directly if there is a specific time you need your driveway access free, and they will accommodate you to the best of their ability. Given there are no unexpected challenges or weather delays, the project is scheduled to be complete near the end of April.
(2) Attached is a letter that was mailed to your address on or near February 13th. By request, the City is willing to reconstruct your driveway provided that 50% of the cost is paid in advanced. The maximum driveway width allowed for a single car garage is 24-ft. For a 24-ft wide access the shared cost at 50% is approximately $300.00. Please let Nicholas or myself know how you would like to proceed by Friday, March 6, 2015.
Sincerely,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
<Stowers_DrivewayAccessLetter.pdf>